Oregon/Jackson Street Bridge Study - Schedule

​​This page outlines the proposed schedule for the Oregon/Jackson Street Bridge Study and any potential improvement project construction. All schedules are subject to change.

Current (this year)

  • WisDOT recently decided to move forward with Alternative M4, a high-level fixed bridge on a partially offset alignment, as our preferred alternative. A draft version of our environmental document is anticipated in Summer 2023.​

Future (next year and beyond)

  • 2024: Approval of environmental document
  • 2025-27: Potential real estate acquisition (dependent on preferred alternative)
  • 2028: Construction begins on selected alternative
  • ​2029/30: Construction complete
  • View overall project schedule in display graphic

Past (anything prior to today)

  • June 2022 - Oshkosh City Council votes 7-0 in favor of high level fixed bridge
  • March 2022 - Oshkosh City Council workshop
  • April 2022 - PIM #3 for environmental study
  • Summer 2021 - WisDOT resumes environmental study
  • Late 2017 - WisDOT suspends environmental study
  • May 2017 - Oshkosh City Council votes 4-3 in favor of Alternative F
  • January 2017 - Oshkosh City Council workshop
  • October 13, 2016 – Public involvement meeting (PIM) #2 for environmental study
  • ​2016/17 – Study discussion and coordination with city of Oshkosh officials
  • April 27, 2016 – ​PIM #1 for environmental study
  • Fall 2015 – Environmental study began