WIS 130 (Wisconsin River Bridge)

Project location | Project overview | Schedule | Traffic impacts/detours | Status/phase | Contact information

Project location

WIS 130 (Wisconsin River Bridge), WIS 23 – Lone Rock, Richland County

Project overview

This is an interim rehabilitation project for the bridge structure while replacement options are studied.

This overhead truss structure spans the North Channel of the Wisconsin River south of Lone Rock on WIS 130 along the border of Richland and Sauk Counties.

The proposed project will consist of strengthening floor beam connections, painting areas of repair, and painting overhead truss members of the structure. Work would be confined to the structure with the exception of steel beam installations to replace the guardrail connections at the four corners of the structure.

Schedule

  • July 9 - August 31, 2018 - Construction scheduled

Traffic impacts/detours

WIS 130 bridge will be closed during construction and traffic will be detoured. The detour route will utilize WIS 23 just north of ZZ across the Wisconsin River to Spring Green, US 14 to WIS 130 on the north end of Lone Rock. A secondary detour route will take WIS 80 traffic to Muscoda on WIS 133/WIS 80, WIS 80 across the Wisconsin River to WIS 60 to WIS 130 on the north end of Lone Rock.

Status/phase

Design

Contact information

Dan Kleinertz, WisDOT Project Manager
(608) 789-5709
daniel.kleinertz@dot.wi.gov

Michael Bie, WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov

Wisconsin Department of Transportation
Southwest Region, La Crosse Office
3550 Mormon Coulee Road
La Crosse, WI 54601
Phone: (608) 785-9022
Fax: (608) 785-9969