Release date: March 20, 2022
To invest in Wisconsin's transportation system, Governor Evers signed a $3.09 million contract to resurface WIS 142 from the west frontage road along I-94 to county J in Kenosha County. Work is scheduled to begin the week of April 4th, weather permitting. The 12-mile-long project will wrap up in July 2022. Payne and Dolan is the prime contractor for the project and will implement the following:
Project Improvements
- Mill existing roadway.
- Overlay roadway.
- New striping.
- Culvert replacement and bridge rehabilitation.
- New signing.
Construction is currently scheduled to begin April 4th and be complete by mid-July 2022. The schedule is dependent on favorable weather conditions and construction progress.
For additional project information visit; SouthEast – 511 WI Projects
For more information regarding southeast region traffic impacts, transportation news and project updates: