Governor Evers approves WIS 142 construction project

​Release date: March 20, 2022 

To invest in Wisconsin's transportation system, Governor Evers signed a $3.09 million contract to resurface WIS 142 from the west frontage road along I-94 to county J in Kenosha County. Work is scheduled to begin the week of April 4th, weather permitting. The 12-mile-long project will wrap up in July 2022. Payne and Dolan is the prime contractor for the project and will implement the following:

Project Improvements

  • Mill existing roadway.
  • Overlay roadway.​
  • New striping.
  • Culvert replacement and bridge rehabilitation.
  • New signing.

Construction is currently scheduled to begin April 4th and be complete by mid-July 2022. The schedule is dependent on favorable weather conditions and construction progress.

For additional project information visit; SouthEast – 511 WI Projects

For more information regarding southeast region traffic impacts, transportation news and project updates: