As the I-41 Project continues through the design and construction phases, key dates impacting the Project will be posted below. Currently, here is what we expect. All dates are subject to change.
- Public information meetings: spring and fall 2020
- Environmental Document complete: April 2021
- Public hearing: May 2021
- Final Environmental approval: Nov 2021
- Final Engineering: 2022-2024
- Right of Way Acquisition: 2023-2024
- Construction: TBD