WIS 116 - Schedule

​Current (this year)

  • Final design Main St. and Wolf River Bridge
  • Real estate acquisition for Main St. (WIS 116) and Wolf River Bridge project

Future (next year and beyond)

  • Public involvement meetings (PIM) - To be determined
  • Real estate acquisition continues for Wolf River Bridge and Main St. projects
  • Summer 2017 – Construction scheduled to start on Wolf River Bridge
  • Early 2018 – Construction scheduled to start on Main St.
  • Late 2018 – New Wolf River Bridge and Main St. scheduled to open to traffic
  • 2019 – Construction of new fishing platforms

Past (anything prior to today)

  • May 3, 2016 - PIM for Wolf River Bridge and Main St. reconstruction projects
  • Nov. 5, 2014 - PIM for Wolf River Bridge and Main St. reconstruction projects
  • Aug. 5, 2014 - Finding of No Significant Impact (FONSI) approval for the Wolf River Bridge Study
  • Oct. 9, 2013 - Public Hearing held for Wolf River Bridge Environmental Study