US 12/18 (Madison Beltline) Seminole Highway to I-39/90

Project location | Project overview | Schedule | Traffic impacts/detours | Status/phase | Contact information

Project location

US 12/18 (Madison Beltline) Seminole Highway to I-39/90, Madison - Dane County

Project overview

This project will place a 2-inch asphalt overlay on the highway surface between Seminole Highway and the Interstate. Structure repairs will be incorporated at the Beltline bridges over US 51 (Stoughton Road) and Todd Drive.

Schedule

  • March to October 2019 - Construction anticipated

Traffic impacts/detours

  • Nighttime work, 8 p.m. – 6 a.m., using single and double lane closures
  • Structure repairs at Todd Drive will require some weekend work.

*Traffic slowdowns possible in early evening work hours.

Status/phase

Design

Contact information

Greg Brecka, P.E., WisDOT Project Manager
(608) 245-2671
gregory.brecka@dot.wi.gov

Michael Bie, WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
Fax: (608) 246-3843
TTY: 711
Email: swr.dtsd@dot.wi.gov