US 14 (WIS 92 to WIS 138) and US 14/WIS 92 intersection

Project location | Project overview | Schedule | Traffic impacts/detours | Status/phase | Contact information

Project location

 US 14 (WIS 92 to WIS 138) and US 14/WIS 92 intersection, Madison - Dane County

Project overview

This project will reconstruct the intersection of US 14 and WIS 92 to a roundabout in order to reduce the history of fatal/severe injuries type crashes. This intersection had seventeen recorded crashes from 2012 through 2016. Of the 17 crashes, 14 were right angle crashes. Those 14 crashes resulted in two suspected serious injuries, two suspected minor injuries, four possible injuries, and six property damage only crashes. The project is being funded through the Highway Safety Improvement Program (HSIP).

The project will also address 4.0 miles of deteriorating pavement on US 14 between WIS 138 and WIS 92 in Dane County. WisDOT is in the process of developing plans to resurface this 4-mile section of US 14 to extend the service life and improve safety. The project will remove and replace the asphalt pavement.

Additional improvements include:

  • Pave asphalt shoulders throughout corridor to improve safety
    • Widen paved shoulders an additional 2 feet
  • Install shoulder rumble strips and centerline rumble strips to improve safety
    • Centerline and shoulder rumble strips will be a new design that helps to reduce noise
  • Installation of gravel shoulders to match the final roadway elevation
  • Installation of pavement marking
  • Installation of new advanced warning signs

Schedule

Past (prior to today)

  • Public involvement meeting (PIM) #1 - October 24, 2018
  • Environmental document - Spring 2019
  • Preliminary plans - July 2019
  • Real Estate acquisition - Fall 2019

Future (2019 and beyond)

  • Final plans submittal - February 1, 2021
  • Construction - Fall 2021 (excavation work at WIS 92 intersection)
    • Spring 2022 (roadway improvements)

Traffic impacts/detours

US 14 will remain open to traffic for majority of roundabout construction

  • US 14 to be closed to through traffic from WIS 138 to WIS 92 for resurfacing improvements and final stage of roundabout construction
    • Closure expected to last approximately one month
    • Posted detour will utilize WIS 138, WIS 59, and WIS 104
  • WIS 92 will also be closed at the US 14 intersection for a portion of the roundabout construction
Detour routes

Status/phase

Design

Contact information

Alex Hagen, P.E., WisDOT Project Manager
(608) 246-3830
alex.hagen@dot.wi.gov

Michael Bie, WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)