Project overview

This project is 4.9 miles in length, begins at intersection of State Highway 23/136 and ends at the north approach of the Narrows Creek Bridge in Rock Springs. The project consists of milling 2-inches of the existing pavement and paving 2-inches of asphaltic pavement, replacing pavement marking and installing centerline rumble strips. New guardrail and barrier will also be installed as part of this project.

Exhibits

Schedule

  • This project is currently scheduled to be constructed in 2019.

Traffic impacts/detours

The road will remain open to traffic for most of the project by using flagging operations. There will be an approximate 2-week closure of State Highway 136 at the Wisconsin & Southern Railroad crossing. The marked detour will be WIS 136 to WIS 154 then to WIS 23.

Status/phase

Design

Contact information

Anthony Vander Wielen, WisDOT Project Manager
(608) 789-7878
anthony.vanderwielen@dot.wi.gov

Michael Bie, WisDOT Southwest Region Communications Manager
(608) 246-7928
michael.bie@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southwest Region, La Crosse Office
3550 Mormon Coulee Road
La Crosse, WI 54601
Phone: (608) 785-9022
Fax: (608) 785-9969
TTY: 711
Email: swr.dtsd@dot.wi.gov