WIS 23

Project location | Project overview | Schedule | Traffic impacts/detours | Status/phase | Contact information

Project location

WIS 23, County Shop Road to Minerva Street, City of Darlington, Lafayette County

Project overview

The Wisconsin Department of Transportation (WisDOT) is in the process of developing plans for  a proposed project on WIS 23 in Lafayette County. The projects begin near the intersection of County Shop Road/WIS 81 in the City of Darlington and  continues north approximately 1.5 miles to the intersection of Minerva Street in the City of Darlington.
   
The purpose of the  project is to resurface and reconstruct WIS 23 south of the Pecatonica River,  improve intersections at Center Hill Road, Union Grove Lane and the Huntington Court, replace the bridge deck over the Pecatonica River, resurface and replace the pavement on WIS 23 north of the Pecatonica River, improve intersections at Harriet Street and Washington Street, and provide a box culvert extension near the Minerva Street intersection. Real estate acquisitions are needed on the project.
 
Additional improvements to these projects include retaining wall additions south of the river, upgrading curb ramps to meet specifications for American Disabilities Act (ADA), water and sanitary utility upgrades, storm sewer upgrades, lighting upgrades, beam guard upgrades, and access modifications.

Schedule

  • October 11, 2018 – Public Involvement Meeting (PIM) #3 (Darlington)
    • 5:30 – 7:30 p.m., Lafayette County Highway Department, 12016 Hill Street, Darlington
  • Design Work
  • Environmental Document – January 2018
  • Design Study Report – June 2018
  • Real Estate Plat – July 2018
  • Appraisal Staking – Fall 2018
     

Future (next year and beyond)

  • PIM #4 – Prior to construction
  • Right-of-way acquisition
  • Spring 2020 – Plans finalized
  • 2021 – Construction anticipated

Past (prior to today)

  • October 11, 2018 – PIM #3 (Darlington)
    • Exhibits (These files are very large and may take several minutes to download)
    • November 15, 2016 – PIM #2 (Darlington)
      • Exhibits (These files are very large and may take several minutes to download)

    Traffic impacts/detours

    During construction, the roadway will be closed to through traffic and detoured. Access to residences and businesses throughout the corridor will be maintained. Access over the Pecatonica River will be maintained for local traffic to access the downtown area.

    Status/phase

    Design

    More information on this project will be provided as the design process continues

    Contact information

    Matthew Dapp, WisDOT Project Manager
    (608) 246-5353
    matthew.dapp@dot.wi.gov

    Michael Bie, WisDOT Southwest Region Communications Manager
    (608) 246-7928
    michael.bie@dot.wi.gov

    Wisconsin Department of Transportation (WisDOT)
    Southwest Region, Madison Office
    2101 Wright Street
    Madison, WI 53704
    Phone: (608) 246-3800
    Fax: (608) 246-3843
    TTY: 711
    Email: swr.dtsd@dot.wi.gov