Release date: July 8, 2024
To invest in Wisconsin’s transportation system, Governor Evers has approved a $1.92 million reconstruction project at the intersection of WIS 75 and County A (Plank Road) in Racine County. Musson Brothers, Inc. is the prime contractor for the project. Construction is scheduled to begin July 15.
Improvements include:
- Construction of new roundabout at WIS 75 and County A (Plank Road) intersection.
- New street lighting.
- New pavement marking and signing.
- Culvert replacement.
Traffic Impacts:
- The WIS 75 and County A (Plank Road) intersection will be closed during construction.
- WIS 75 detour will utilize WIS 20, US 45, and WIS 11.
- Access to local businesses and residences will be maintained.
Work is scheduled for completion in fall 2024. All work is weather dependent and subject to change.
For more information, contact:
Chris Verhyen
WisDOT Southeast Region Communications Manager
(262) 548-8757