Completed WIS 125/College Avenue design-build project
WisDOT's first design-build pilot project is complete. The structure on WIS 125/College Avenue in the town of Grand Chute, Outagamie County, reopened to traffic Oct. 31, 2023, within budget and on a compressed schedule.
- Cost: $3.8 million
- Two months to complete
- Structure replacement on WIS 125 over Mud Creek just east of I-41
- Replacement of box culvert and work on pavement, curb and gutter, storm sewer and beam guard
WisDOT is looking closely at how design-build contracts can minimize construction impacts while delivering quality work. That learning process is ongoing as the department continues to evaluate design-build as an alternative contracting method. Congratulations to the project team
WIS 125 6526-00-71 - Project Description
- I-41 – Bluemound Dr., Outagamie County, Northeast Region
- Removal of a multi-cell box culvert and replacement with a slab span structure on College Avenue in Appleton
-
WIS 125 Best Value Score Results
- Proposals received: August 19, 2022
- Results posted: September 9, 2022
- The Highest Adjusted Score is the Best Value Proposal and the project will be awarded to the associated design-builder.
Design- Builder | Technical Proposal Score | Cost Proposal Amount |
Amount Exceeding Lowest Proposal |
Percent Exceeding Lowest Cost Proposal | Price Score | Adjusted Score |
Pheifer Bros | 30.51 | $3,806,945.86 | - | N/A | 60 | 90.61 |
KNA | 31.8 | $5,247,705.00 | $1,440,759.14 | 37.85% | 37.29 | 68.47 |
- Schedule
- May 27, 2022 - Clarification Submittal #1 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
- June 2, 2022 - One-on-One Meeting on RFP and Initial ATCs
- June 7, 2022 - DBE Meet and Greet
- June 17, 2022 - Clarification Submittal #2 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
- June 23, 2022 - One-on-One Meeting on RFP and Initial/Final ATCs
- July 1, 2022 - Initial ATC Submittal Deadline (5:00 pm Central Time)
- July 8, 2022 - Department ATC Response Date
- July 29, 2022 - ATC Resubmittal Deadline (5:00 pm Central Time)
- August 1, 2022 - Final Clarification Deadline (5:00 pm Central Time)
- August 1, 2022 - SOQ Modification Request Deadline (5:00 pm Central Time)
- August 5, 2022 - Department ATC Final Response Date
- August 10, 2022 - Department SOQ Modification Request Response Date
- August 10, 2022 - Department Clarification Response Date
- August 19, 2022 - Proposal (Technical Proposal and Price Proposal) Due Date (3:00 pm Central Time)