Location
US 10 eastbound, Appletree Lane to Old WIS 49, Waupaca County
Project Overview
The purpose of the project is to restore deteriorated surface pavement to extend the roadway service life, replace deteriorating culverts, replace substandard guardrail, perform minor bridge repairs and signal updates.
Traffic Impacts
Mainline work will be done using single-lane closures of US 10. Ramp work will be done using detours to adjacent ramps. Work at the WIS 96 and 110 intersection will be staged with lane closures. See details below in the Public Involvement section.
Real Estate
No Real Estate acquisition is anticipated
Project Schedule
- Public Involvement: November 2023
- Design Study Report: May 2024
- Finalized Design: August 2025
- Construction is currently scheduled as early as summer 2026 or summer 2028
Public Involvement
Letters have been sent to affected property owners. This project involves several traffic control methods. Below are details of each of the traffic control methods that were shared: