Racine St. Bridge Replacement - Schedule

Schedule is tentative and subject to change

Current

  • October 2018 – Real estate acquisition for project begins

Future (next year and beyond)

  • Summer 2020 – Construction scheduled to start on selected alternative
  • Late 2022 – Construction complete for selected alternative

Past (anything prior to today)

  • November 28, 2018 - Public involvement meeting #3 for selected alternative
  • October 9, 2018 - Federal Highway Administration (FHWA) approves environmental document
  • October 2, 2018 - FHWA approves Section 4f document
  • June 4, 2018 - Environmental and Section 4f documents submitted to FHWA for approval
  • May 14, 2018 - Environmental and Section 4f documents submitted to FHWA for approval 
  • Late 2015 – WisDOT selects Alternative J as preferred alternative
  • Nov. 2, 2015 - Menasha City Council votes to support Alternative J
  • June 17, 2015 - Public involvement meeting #2 for environmental study
  • October 29, 2014 – Public involvement meeting #1 for environmental study
  • January 2014 – Environmental study begins
  • Fall 2012 – Completion of feasibility study