US 45 Resurfacing (7th Avenue to WIS 20) - Racine County

project location  

Overview:

The Wisconsin Department of Transportation (WisDOT) is proposing to resurface approximately 3.5 miles of US 45, from 7th Avenue to WIS 20, in Racine County.

Proposed Improvements:

  • Resurface US 45 within project limits (7th Avenue to WIS 20)
  • Replace curb ramps to meet current ADA standards
  • Drainage structure repairs and cleaning
  • New pavement marking and signing

Proposed Traffic Impacts:

  • US 45 will remain open during construction under flagging operations
  • Short-term, full closure of the US 45/County C roundabout (approx. 4 days)
    • Detour route will be provided during roundabout closure via WIS 11, I-94, and WIS 20

Schedule:

Construction is scheduled to begin in 2027.

Status:

Design phase - if you have any comments or questions regarding this project, please feel free to contact the project representatives listed below.

Contact Information:

Jon Gill
WisDOT Design Project Manager
(262) 548-8812
Jonathan.Gill@dot.wi.gov

Chris Verhyen
WisDOT SE Region Communications
(262) 548-8757
Chris.Verhyen@dot.wi.gov