WIS 60 Resurfacing Project (County P to Eagle Drive) / WIS 60 and Eagle Drive Roundabout - Washington County

Location

WIS 60 from County P to Eagle Drive in the Village of Jackson, Washington County.

Overview

The existing pavement surface in the corridor is severely deteriorated and requires treatment to extend the service life of the roadway. Proposed improvements include:

  • New HMA (Hot Mix Asphalt) pavement surface, new pavement markings, and signage
  • Upgrade traffic signals at County P, Industrial​ Drive and Jackson Drive
  • Improve curb ramps to ADA standards
  • Reconstruct WIS 60 at Eagle Drive intersection to a modern roundabout with HMA (Hot Mix Asphalt)
  • Extending the existing 48-inch twin culvert pipes located on the north leg of Eagle Drive
  • Installation of retaining wall at the northwest corner of the roundabout

Public Involvement Meeting

A virtual public involvement meeting was held in the summer of 2021. Please view the virtual public involvement meeting materials and exhibits below:

Schedule

Construction is currently scheduled for 2024.

Traffic Impacts

One-way traffic patterns in the eastbound direction with detour for westbound traffic, full roadway closure with detours and two-way traffic patterns under flagging operations.

Status

Design phase - Do you have any comments or questions? We'd like to hear from you! Please feel free to contact the project representatives below.

Contact Information

Drew Pinter
PE, WisDOT Project Manager
(262) 548-6438
Andrew.Pinter@dot.wi.gov

Chris Verhyen
WisDOT Communications Manager, SE Region
(262) 548-8757
Chris.Verhyen@dot.wi.gov