Project Overview
The Wisconsin Department of Transportation (WisDOT) is proposing a resurfacing and improvements project along approximately 1.1 miles of WIS 67 (Lincoln Street) between I-43 and Walworth Street, in the city of Elkhorn, Walworth County.
Proposed Improvements
- Mill and resurfacing about 1.1 miles of roadway, including pavement repairs.
- Replace traffic signals at the WIS 67 (Lincoln Street) and Geneva Street intersection.
- Update curb ramps to meet ADA standards
- Box culvert maintenance
- Coordinate with Wisconsin & Southern Railroad to replace crossing pavement, signals, and gates.
Proposed Traffic Impacts
Traffic impacts are still being determined. Additional information will be posted here when available.
Public Involvement
Public involvement is a vital part of all WisDOT projects. Please view the project documents and exhibits below. If you have any comments or questions, please fill out a comment form or contact the project representatives listed below. Please provide comments by January 9, 2026.
Schedule
This project is in the design phase with construction tentatively scheduled for 2031. Work may be advanced to 2029, if funding becomes available. If you have any comments or questions about this project, please contact the project representatives listed below.
Contact Information
Bob Bellin, P.E.
WisDOT Project Manager
(262) 521-4405
Robert.Bellin@dot.wi.gov
Chris Verhyen
WisDOT SE Region Communications
(262) 548-8757
Chris.Verhyen@dot.wi.gov