Project location
I-39/90/94 (WIS 60 to County CS), Arlington to Poynette - Columbia County
Project overview
This project will patch existing concrete, replace beam guard, and clean drainage pipes on I-39/90/94 in Columbia County. A mill and overlay will take place on County CS at the interchange with I-39/90/94.
Schedule
- June 2024 - Public input requested
- 2027 - Construction anticipated
Traffic impacts/detours
I-39/90/94 will have off-peak lane closures and limited ramp closures for the duration of construction. Work on County CS will take place as a flagging operation.
Status/phase
Design
Contact information
Greg Brecka, P.E.
WisDOT Project Manager
(608) 516-6524
gregory.brecka@dot.wi.gov
Hannah Punzel
WisDOT Southwest Region Communications Manager
(608) 246-7907
hannah.punzel@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
TTY: 711
Email:
swr.dtsd@dot.wi.gov