Release date: July 3, 2026
The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Ashland County
Prentice Avenue
- Location: US 2 (Lake Shore Drive) to 6th Street East in Ashland
- Schedule: May 4 to early June
- Cost: $845,876
- Description of work: Replacing the existing pavement structure, making subgrade improvements, modifying the vertical profile of the road to allow for better tie-ins, replacing substandard curb ramps, curb and gutter, adding two inlets just south of 3rd Street and replacing pavement markings and signage
- Traffic impacts: Prentice Avenue is closed.
County GG
- Location: McCarthy Creek Bridge southwest of Mellen
- Schedule: May 26 to late July
- Cost: $665,275
- Description of work: Replacing the bridge, reconstructing the pavement on both sides of the bridge and replacing guardrail
- Traffic impacts: County GG is closed from Conley Road to Clam Lake Road
- Traffic is being detoured via WIS 13 and WIS 77.
Ashland and Sawyer counties
WIS 13 and WIS 77
- Location: WIS 13, Price County line to Morse Road between Mellen and Glidden, and WIS 77, Teal River Bridge northeast of Hayward
- Schedule: WIS 13, April 27 to late October; Work on WIS 77 expected to start in August
- Cost: $5.19 million
- Description of work: WIS 13, replacing, resetting, extending or abandoning more than 50 existing culvert pipes and constructing a new box culvert at Becky Creek; making concrete surface repairs at the bridge over Dryden Creek northwest of Glidden; patching the deck on the bridge over the Chippewa River southeast of Glidden; overlaying the deck with concrete on the bridge over Butternut Creek south of Butternut; and replacing guardrail at the structures and one other location in the project limits; WIS 77, milling and overlaying the existing bridge deck, overlaying concrete pavement approach slabs, milling and overlaying roadway approaches, making concrete surface repairs on parapets, grouting voids under abutments, supplementing riprap at abutments, adjusting guardrail and installing new pavement markings
- Traffic impacts: WIS 13 remains open to traffic, but motorists will encounter:
- Single-lane closures controlled by temporary traffic signals at Becky Creek and active culvert pipe installations
- Signals at Becky Creek are in place continuously and will be active through the holiday weekend.
- Those at culvert pipe locations are in place during work hours only and won’t be in place for the holiday weekend.
- Single-lane closures controlled by flagging during paving at culvert sites will resume the week of Monday, July 6.
Barron County
County O
- Location: East Branch Upper Pine Creek Bridge north of the village of Dallas
- Schedule: June 15 to early August
- Cost: $ $501,425
- Description of work: Replacing the bridge and reconstructing 149.5 feet of approaching roadway
- Traffic impacts: County O is closed at the structure, and traffic is being detoured via County D, WIS 25 and County U.
County O
- Location: Wisconsin Avenue intersection in Rice Lake
- Schedule: April 20 to late September
- Cost: $1.1 million
- Description of work: Realigning and extending the County O left-turn lanes, constructing right-turn lanes both north and south along Wisconsin Avenue, replacing traffic signals and adding sidewalk and a pedestrian crossing on County O
- Traffic impacts: None.
US 53 South
- Location: Bridges between Cameron and New Auburn: structures over US 8, Knapp Street, County A, County AA and Carlson School Road, 2025, and structures over 20th Street, County I and the Chetek River, 2026
- Schedule: Feb. 23 to October, 2026 construction; and May 5, 2025, to October 2026, overall project
- Cost: $10.91 million
- Description of 2026 work: Replacing the decks on the bridges over the Chetek River and 20th Street; replacing the bridge over County I; milling pavement on both sides of each structure and placing new asphalt pavement on the approaches; milling and overlaying the pavement on the southbound US 53 on- and off-ramps at the County I interchange; and replacing guardrail, pavement markings and signage
- Traffic impacts: Southbound US 53 remains open to traffic, but motorists will encounter:
- Single-lane closures on southbound US 53 and a reduced speed limit of 60 mph.
- Single-lane closures on County I through the duration of the project
- Closure of the ramp from County I to southbound US 53
- Traffic is being detoured on northbound US 53 to the US 8 interchange, where motorists will exit and then re-enter southbound US 53.
- The ramp closure is anticipated to be in place through late September.
US 63
- Location: Charrie Lane in Cumberland to the Washburn County line
- Schedule: April 13 to late June
- Cost: $$4.64 million
- Description of work: Removing a portion of the existing pavement and paving new asphalt, installing centerline and edge line rumble strips, cleaning or repairing culverts, reconstructing sidewalk curb ramps to Americans With Disabilities Act (ADA) compliance and placing new pavement markings
- Traffic impacts: None.
- Lane closures controlled by flagging might resume as finishing work is completed next week.
US 63
- Location: Beaver Dam Lake
- Schedule: April 24 to early September
- Cost: $2.64 million
- Description of work: Removing the existing box culvert carrying Beaver Dam Lake under US 63, building a bridge with a longer span to replace the box culvert, removing the Lake Street Bridge, dredging Beaver Dam Lake under US 63 and the Lake Street Bridge, building an ATV trail on the east side of US 63 from Arcade Avenue to Nedvidek Street, reconstructing US 63 on both sides of the new bridge, reconstructing portions of Lake Street, Nedvidek Street and Babcock Avenue to match the raised profile of US 63 and constructing curb, gutter and sidewalk
- Traffic impacts: US 63 is closed to traffic on both sides of the structure.
- Traffic is being detoured via WIS 48, US 53 and WIS 70.
- In addition, Lake Street is closed just past the boat landing.
- Access to the boat landing is being maintained.
- The Lake Street Bridge is open to emergency vehicles only through late July.
Bayfield County
WIS 13
- Location: Little Whittlesey Creek
- Schedule: June 8 to mid-October
- Cost: $1.5 million
- Description of work: Constructing a temporary bypass to carry WIS 13 traffic during construction, replacing the culvert pipes with a bridge, milling and paving about 1,000 feet of pavement approaching the bridge, restoring the stream bed, installing new guardrail, relocating the driveway of the US Fish and Wildlife Service facility, adding riprap and removing the temporary bypass
- Traffic impacts: WIS 13 remains open to traffic, but motorists are using a temporary bypass to travel around the construction site.
US 2
- Location: North Fish Creek Bridge southwest of the intersection of US 2 and WIS 13
- Schedule: April 13 to mid-July
- Cost: $1.69 million
- Description of work: Replacing the bridge deck, repairing an abutment, resetting an inlet, completing minor paving on both sides of the bridge to adjust and smooth out roadway approaches and adjusting guardrail
- Traffic impacts: US 2 is reduced to a single lane at the bridge.
- The open lane has a maximum width of 13 feet.
- Temporary traffic signals are controlling use of the single lane.
- Motorists should expect delays.
- The alternative oversize-overweight truck route follows US 53, WIS 77, WIS 13 and WIS 112.
Buffalo County
County P
- Location: Trempealeau River Bridge east of Fountain City in the town of Buffalo
- Schedule: Feb. 23 to mid-October
- Cost: $1.78 million
- Description: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing the temporary bypass and structure.
- Traffic impacts: Motorists are using a temporary road and bridge to bypass the work zone.
- They might encounter flagging at the site for hauling in equipment and materials.
- In addition, buoys have been added upstream and downstream to alert boating traffic of construction.
WIS 35 and WIS 54
- Location: WIS 35, Indian Creek Road to old WIS 35; and WIS 54, Minnesota state line to WIS 35
- Schedule: April 23 to early July
- Cost: $6.41 million
- Description of work: WIS 35: Milling and overlaying the asphaltic pavement; repairing or replacing culverts to address deterioration; adjusting, repairing or replacing guardrail; improving drainage along WIS 35 just west of Lovers Lane; upgrading curb ramps to meet Americans With Disabilities Act standards; installing centerline and shoulder rumble strips; and adding new pavement markings; WIS 54: Milling and overlaying the asphaltic pavement, replacing weigh-in-motion sensors in the roadway; installing centerline and shoulder rumble strips; and adding new pavement markings
- Traffic Impacts: None.
- Lane and shoulder closures on WIS 35 and WIS 54 controlled by flagging might resume Monday, July 6.
US 10
- Location: Pepin County line to County A in Mondovi
- Schedule: June 30 to late August
- Cost: $3.35 million
- Description of work: Milling the pavement surface and overlaying the roadway with asphalt, installing centerline rumble strips; replacing guardrail and flattening slopes at guardrail end terminals; cleaning, repairing or replacing culvert pipes; cleaning ditches to remove sediment buildup; and installing new pavement markings
- Traffic impacts: US 10 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging.
- Construction operations will cease by noon today, and there will be no lane restrictions for the holiday weekend.
- Single-lane closures will resume Monday, July 6.
Burnett County
WIS 35
- Location: Lanquist Street in Siren to WIS 70 East
- Schedule: May 4 to mid-October
- Cost: $8.55 million
- Description of work: Replacing pavement with new concrete from Lanquist Street to Southshore Drive, replacing storm sewer and expanding its capacity from Lanquist to Works Progress Street, resurfacing the roadway from Southshore Drive to WIS 70 East, reviewing and revising access points, improving turning movements in all quadrants at the WIS 35 and WIS 70/County B intersection in the city of Siren, replacing traffic signals, replacing curb ramps and removing extra lanes from Park Street to Northshore Drive to reduce flooding potential
- Traffic impacts: Once work resumes Tuesday, May 26, motorists will encounter:
- Shoulder closures on northbound WIS 35 from Lanquist Street to Bradley Street; southbound WIS 35 from the WIS 35/70 intersection to Bacon Street; and east- and westbound WIS 70 from 1st Avenue to the WIS 35/70 intersection
- Shoulder closures on north- and southbound US 53 from Southshore Drive to WIS 35/70 roundabout
- WIS 35 is only open to southbound traffic from Lanquist Street to Southshore Drive, and northbound car and heavy truck traffic is being detoured.
- Northbound car detour: County B, 4th Avenue North and Elizabeth Street
- Truck detour: WIS 70/MN 70, I-35 (MN), MN 48/WIS 77 and WIS 35
Chippewa County
205th Avenue
- Location: McCann Creek Bridge northeast of Bloomer
- Schedule: May 4 through early July
- Cost: $522,421
- Description of work: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing the temporary bypass and structure
- Traffic Impacts: Traffic has been moved to the new structure, but motorists might encounter lane closures as finishing work is completed.
- Construction is anticipated to be completed by early next week.
WIS 124
- Location: Duncan Creek Bridge to County S
- Schedule: April 13 to mid-June
- Cost: $2.68 million
- Description of work: Milling off a portion of the pavement and placing new asphalt pavement, resurfacing the County S roundabout and replacing the central island truck apron pavement, replacing culverts, cleaning ditches, upgrading sidewalk curb ramps and replacing pavement markings
- Traffic Impacts: None; current operations have ceased until Monday, July 20, when work is set to begin on the WIS 124/County S roundabout.
- During work on the roundabout - anticipated to run from July 20 through Thursday, Aug. 6, the roundabout will be closed.
- Traffic will be detoured via Business 29 (West River Street), US 53 and County B.
US 53
- Location: 40th Avenue in Lake Hallie to County B in the town of Tilden
- Schedule: March 2 to late June, 2026 construction; and April 1, 2024, to late June 2026, overall project
- Cost: $36.6 million
- Description of 2026 work: Replacing the pavement on southbound US 53 south of County N, widening the shoulder on the ramp from Business 29/County X to southbound US 53, placing polymer overlays on the southbound US 53 bridges over the Chippewa River and BUS 29/County X, replacing guardrail, completing culvert work, building permanent maintenance crossovers, installing new pavement markings and shoulder rumble strips and removing temporary crossovers used during construction
- Traffic Impacts: None; project complete.
Chippewa and Clark counties
WIS 29
- Location: 320th Street east of Boyd to Koser Avenue west of Thorp
- Schedule: May 11 to mid-September
- Cost: $9.35 million
- Description of work: Patching the concrete pavement, placing 3.75 inches of asphalt over the existing roadway, removing a portion of the existing pavement on the WIS 29 on- and off-ramps at the County H interchange in Stanley and on County H between the east- and westbound ramps and placing new asphalt pavement, repairing culverts as needed, rehabilitating the structure over Hay Creek east of Boyd and closing and removing the intersection on WIS 29 at 320th Street per the town of Delmar’s request
- Traffic impacts: WIS 29 remains open to traffic, but motorists will encounter single-lane closures in both directions for the entire length of the project.
- Construction operations will cease by noon today, and there will be no lane restrictions for the holiday weekend.
- Single-lane closures will resume Monday, July 6.
Clark County
WIS 29
- Location: County D in Owen to WIS 13 in Abbotsford
- Schedule: March 30 to early October
- Cost: $17.37 million
- Description of work: Repairing the existing concrete pavement on WIS 29 and the ramps at the County E interchange and then overlaying the roadway and ramps with asphalt pavement; overlaying the ramps at Cardinal Avenue east of Owen and Hi Line Avenue in Abbotsford with asphalt; replacing guardrail to meet current WisDOT standards; repairing the decks on the east- and westbound WIS 29 bridges over County D and the railroad tracks to the east and placing a thin bonded polymer overlay over them; cleaning and repairing culverts to improve drainage; repairing the median inlets near Owen adjacent to concrete barrier wall; and completing minor grading of ditches
- Traffic Impacts: None.
- Single-lane closures in both directions resume Monday, July 6.
WIS 98
- Location: WIS 73 south of Greenwood to Helm Street in Loyal
- Schedule: July 2 through mid-September
- Cost: $1.8 million
- Description of work: Replacing the existing concrete pavement in select areas of pavement failure due to poor soils; replacing base material and adding geo-grid in those poor soils areas; making concrete joint repairs in other areas; replacing, repairing, resetting, extending or cleaning culvert pipes; and replacing pavement markings
- Traffic Impacts: WIS 98 remains open to traffic, but motorists will encounter single-lane closures controlled by flagging operations.
- Construction operations will cease by noon today, and there will be no lane restrictions for the holiday weekend.
- Single-lane closures will resume Monday, July 6.
Douglas County
County B
- Location: Lake Nebagamon Creek Bridge east of US 53
- Schedule: May 18 to mid-July
- Cost: $565,907
- Description of work: Replacing the bridge, reconstructing pavement on both sides of the bridge and grading
- Traffic Impacts: County B is closed at the bridge.
WIS 13
- Location: Bridge over US 2/53 southeast of Superior
- Schedule: June 8 to late July
- Cost: $1.43
- Description of work: Replacing bridge joints, making surface repairs to abutments, cleaning and painting bridge girders and bearings, replacing concrete approach slabs at each end of bridge, replacing asphalt roadway approaches for about 100 feet and replacing the guardrail bridge connections
- Traffic Impacts: WIS 13 and US 2/53 remain open to traffic, but WIS 13 is reduced to a single lane of traffic on the bridge controlled by temporary traffic signals.
WIS 105
- Location: Unnamed tributary of the Pokegama River in Superior
- Schedule: June 15 to late October
- Cost: $3.06 million
- Description of work: Removing the existing culvert, building a temporary bypass to carry a single lane of traffic during construction, constructing a bridge to replace the culvert, replacing pavement approaching the new structure, installing guardrail, removing the temporary bypass and repairing slopes disturbed by construction
- Traffic Impacts: WIS 105 remains open to traffic, but motorists are using a single-lane bypass controlled by temporary traffic signals.
- Truck traffic is being detoured.
- Truck traffic heading west will be detoured north to US 2 and MN 23 at 61st Street and Tower Avenue.
- Truck traffic heading east will be detoured north to MN 23 and US 2 and MN 23 and East McCuen Street in Duluth, Minn.
Dunn County
County P
- Location: Irving Creek west of Menomonie
- Schedule: May 18 to early July
- Cost: $547,773
- Description of work: Replacing the structure with a twin-cell box culvert and reconstructing pavement on both sides of the new structure
- Traffic Impacts: County P is closed at the bridge.
County Q
- Location: North Branch Wilson Creek Bridge northwest of Knapp
- Schedule: June 8 to late July
- Cost: $430,297
- Description of work: Replacing the bridge and reconstructing pavement on both sides of the new structure
- Traffic Impacts: County Q is closed at the structure.
WIS 25
- Location: I-94 in Menomonie to County D
- Schedule: April 16 to early August
- Cost: $4.98 million
- Description of work: Removing a portion of the existing pavement from the bridge over I-94 to the railroad bridge and placing new asphalt pavement; recycling a portion of the existing pavement, mixing it with a stabilizing agent, relaying it and placing new asphalt over the roadway from the railroad bridge to County D; adjusting or replacing guardrail; and upgrading pedestrian curb ramps and traffic signals
- Traffic Impacts: WIS 25 is open to traffic, but motorists will encounter single-lane closures controlled by flagging from the east leg of County BB to County D on the north end of the project.
- Construction operations will cease by noon today, and there will be no lane restrictions for the holiday weekend.
- Starting July 6, crews will begin paving the area between I-94 and County BB from 7 p.m. to 9 a.m.
WIS 85
- Location: Just west of the north junction of County O west of Rock Falls to approximately 2,100 feet west of 1010th Street northeast of Caryville
- Schedule: April 27 to mid-August
- Cost: $3.94 million
- Description of work: Removing a portion of the existing pavement from just west of the north junction of County O to the south junction of County H and placing new pavement, removing and recycling a portion of the existing pavement from the south junction of County H to approximately 2,100 feet west of 1010th Street and overlaying the roadway with new pavement, widening the paved shoulders from 3 to 5 feet, installing centerline and shoulder rumble strips from the south junction of County H to about 2,100 feet west of 1010th Street, replacing the existing drainage structure under WIS 85 east of the north junction of County H with a dual box culvert, replacing a cattle pass that is no longer used with a culvert pipe, removing guardrail and improving the Chippewa River State Trail crossing to meet Americans With Disabilities Act standards
- Traffic Impacts: WIS 85 is closed to through traffic from County O to Fuller Road.
- Through traffic is being detoured via WIS 37 and US 10.
- Access is being maintained to homes and businesses in the work zone.
- Motorists will encounter lane closures controlled by flagging operations where cold-in-place recycling operations are occurring in the work zone.
- WIS 85 is scheduled to reopen to traffic Friday, July 10
US 12 and WIS 40
- Location: US 12: Princeton Drive in Elk Mound to just north of WIS 29; and WIS 40, US 12 to County M in the village of Colfax
- Schedule: March 30 to October
- Cost: $8.99 million
- Description of work: Milling 2.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in rural areas; milling 3.25 inches of existing asphalt and paving 3.25 inches of hot-mix asphalt in urban areas; replacing joints on the Eighteen Mile Creek Bridge in village of Colfax; placing centerline rumble strips in rural areas; replacing cross culverts, guardrail and sidewalk curb ramps; and replacing the railroad crossing in the village of Colfax
- Traffic Impacts: Motorists will encounter single-lane closures controlled by flagging operations from Elk Mound through Colfax.
Eau Claire County
Gravel Pit Road
- Location: Hay Creek Bridge north of Augusta
- Schedule: May 26 to early July
- Cost: $396,980
- Description of work: Replacing the bridge and reconstructing roadway on both sides of the structure
- Traffic Impacts: Gravel Pit Road is closed at the bridge.
WIS 93, WIS 312 and US 12
- Location: WIS 93: East Hamilton Avenue, Eau Claire, to Deerfield Road, town of Washington; WIS 312: Old Wells Road to US 53, all in Eau Claire; and US 12: Truax Boulevard, Eau Claire, to Mayer Road, Altoona
- Schedule: March 30 to mid-September
- Cost: $2.91 million
- Description of work: Reconstructing noncompliant curb ramps and upgrading pedestrian crossings that aren’t consistent or not fully provided where needed
- Traffic Impacts: None, but pedestrians might be directed to use temporary accommodations.
- Once work resumes Monday, July 6, motorists will encounter:
- Single-lane closures on eastbound US 12 at University Avenue, which will be fully open by 11 a.m. daily
- Single-lane closures on westbound US 12 at London Road
I-94
- Location: US 53 interchange to Mallard Road southwest of Eau Claire
- Schedule: March 23 to late November, 2026 construction; and March 4, 2024, to late November 2026, overall project
- Cost: $69.9 million
- Description of 2026 work: Replacing the pavement on eastbound I-94 from Otter Creek to Mallard Road, the eastbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under eastbound I-94 near County D; completing shoulders, removing temporary lanes and structures and restoring the interstate’s median
- Traffic impacts: Motorists will encounter lane closures in both directions during off-peak travel times.
- The speed limit has been reduced to 60 mph in the work zone.
- County D is closed at I-94.
- Traffic is being detoured via US 53, County D, County IJ and County JJ.
Jackson County
Cain Road
- Location: North Branch Trempealeau River Bridge north of Hixton
- Schedule: June 29 through early October
- Cost: $665,514
- Description of work: Building a new bridge north of the existing alignment, reconstructing approximately 1,020 feet of roadway approaches, excavating a marsh, grubbing, placing riprap and removing the existing structure
- Traffic Impacts: The north shoulder is closed.
Pepin County
Dorwins Mill Road
- Location: Bear Creek Bridge east of Durand
- Schedule: May 18 to late July
- Cost: $679,659
- Description of work: Replacing the bridge and reconstructing roadway on both sides of the structure
- Traffic Impacts: Dorwins Mill Road is closed at the bridge.
Polk County
WIS 46
- Location: US 8 to WIS 35
- Schedule: April 15 to early October
- Cost: $8.49 million
- Description of work: Recycling 4 inches of pavement in place on the rural portion of the project; placing 2.75 inches of new asphalt and installing centerline rumble strips; milling 3.25 inches of pavement in the village of Balsam Lake and placing 3.35 inches of new asphalt; cleaning, extending, lining or replacing culverts; replacing or adjusting existing guardrail; and replacing curb ramps in the village of Balsam Lake
- Traffic impacts: WIS 46 is closed from 140th Avenue to 150th Avenue.
- This closure is anticipated to be in place through mid-July.
- Traffic will be detoured via US 8 and WIS 35.
- Motorists might encounter single-lane closures controlled by flagging on other segments of the project.
US 8
- Location: WIS 35 North to WIS 46 South
- Schedule: May 11 to late August
- Cost: $7.52 million
- Description of work: Milling 2.25 inches of existing asphaltic surface and placing 3.25 inches new asphalt; reconstructing two locations of roadway where sloughing is occurring; widening the paved shoulders from 3 to 5 feet; installing centerline and shoulder rumble strips; cleaning, extending, lining or replacing existing culverts and replacing deteriorating end walls on some structures; replacing or adjusting guardrail; and completing roadside maintenance, including clearing and ditching
- Traffic impacts: None.
- Single-lane closures controlled by flagging operations and a pilot car resume Monday, July 6.
- Motorists should expect delays.
Rusk County
US 8
- Location: Little Soft Maple Creek northwest of Weyerhaeuser
- Schedule: June 23 to late September
- Cost: $1.92 million
- Description of work: Constructing a temporary bypass on the north side of US 8 to carry traffic during construction, removing the existing box culvert, constructing a single-span bridge half at a time to replace it, replacing roadway approach pavement on both sides of the structure and installing guardrail
- Traffic impacts: US 8 remains open to a single-lane of traffic controlled by temporary traffic signals.
St. Croix County
WIS 35/64 and WIS 64
- Location: WIS 35/64, 150th Avenue northeast of Houlton to County C, and WIS 64, WIS 35 to 142nd Street in New Richmond
- Schedule: April 13 to September
- Cost: $9.96 million
- Description of work: Performing spot repairs on the driving lanes in both directions where deterioration exists, overlaying existing concrete with asphalt at select locations in both directions of travel, installing new pavement markings and shoulder rumble strips, resurfacing the existing shoulders, replacing guardrail at structures and signage and cleaning or riprapping culvert end walls
- Traffic Impacts: WIS 35/64 and WIS 64 remain open to traffic, but motorists will encounter lane closures throughout the project limits.
- Construction operations will cease by noon today, and there will be no lane or interchange restrictions during the holiday weekend.
- Single-lane closures will resume Monday, July 6.
- Starting Tuesday, July 7, the eastbound County C entrance ramp will be closed.
- The ramp is expected to reopen mid- to late week the week of July 13.
WIS 128
- Location: US 12 to WIS 170 in Glenwood City
- Schedule: May 26 to late August
- Cost: $6.08 million
- Description of work: Recycling 3.75 inches of the existing asphaltic surface and paving 2.75 inches over the recycled pavement in the rural section of the project; milling approximately 3.25 inches of the existing asphaltic surface and paving the roadway with 3.25 inches of hot-mix asphalt in the urban section; placing centerline rumble strips; overlaying the deck on the bridge over Tiffany Creek in Glenwood City; updating guardrail throughout the project corridor; cleaning or replacing culvert pipes; updating sidewalk curb ramps in Glenwood City; and installing new pavement markings
- Traffic Impacts: WIS 128 is open to traffic, but motorists will encounter lane closures controlled by flagging.
- Construction operations will cease by noon today, and there will be no lane restrictions for the holiday weekend.
- Lane closures will resume Monday, July 6.
US 12
- Location: CNW railroad bridge east of Hudson
- Schedule: April 13 to late June
- Cost: $1.24 million
- Description of work: Replacing the concrete bridge deck, making concrete surface repairs at the abutments and girders, replacing the steel bearings at the east abutment, replacing the east abutment expansion joint, replacing the southwest wing wall top, replacing concrete pavement approach slabs and about 100 feet of roadway approaches and placing new pavement markings
- Traffic Impacts: None; project complete.
I-94
- Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson
- Schedule: March 30 to mid-October, 2026 construction; and Sept. 9, 2024, to mid-October 2026, overall project
- Cost: $20.08 million
- Description of 2026 work: Removing and replacing the eastbound I-94 bridges; replacing I-94 pavement on both sides of structures in both directions; installing storm sewer; replacing guardrail and pavement markings; removing temporary structures and travel lanes; and restoring the median
- Traffic Impacts: I-94 remains open to traffic, but motorists will encounter the following on:
- Eastbound I-94 traffic is operating on temporary lanes built in the median in the 100th Street and Kinney Road work zones.
- The speed limit in both work zones has been reduced to 60 mph.
- Starting the night of Monday, July 6, motorists on eastbound I-94 will encounter nightly single-lane closures at 100th Street to facilitate asphalt paving.
- The morning of Wednesday, July 8, motorists on westbound I-94 will encounter single-lane closures at Kinney Road for guardrail repair.
I-94
- Location: St. Croix River bridges between Hudson and Lakeland, Minn.
- Schedule: April 6 to late October, 2026 construction; Sept. 29, 2025, to late October 2026, overall construction
- Cost: $9.85 million
- Description of 2026 work: Construction on both bridges includes: Replacing the modular and expansion joints, placing a new polymer overlay on the bridge decks, making concrete surface repairs, cleaning of bridge bearings and replacing pavement markings. Construction on the westbound bridge also includes: Making repairs on the east and west abutment back walls, completing spot painting of bridge pin and hanger system. Construction on the eastbound bridge also includes: Repairing the east abutment back wall and replacing the sidewalk railing. Construction on the retaining wall on the Wisconsin approach: Replacing the block wall crossing under and adjacent to I-94 and parallel to the pedestrian path.
- Traffic impacts: I-94 remains open to traffic, but motorists will encounter the following on:
- Eastbound I-94:
- Three lanes are open to traffic, with lanes reduced to an 11-foot width.
- Westbound I-94:
- Traffic is reduced to two lanes, with one lane shifted across the median onto eastbound I-94.
- The westbound traffic split will begin near the 11th Street overpass in Hudson.
- The traffic split begins near the 11th Street overpass.
- Hudson to Lakeland/Afton Trail:
- The trail is anticipated to close to users Monday, June 22 just north of the westbound I-94 bridge on the Wisconsin side and just south of the eastbound bridge on the Minnesota side.
- During closure of the trail, a shuttle service will make three roundtrips across the bridges daily, picking up passengers on the Wisconsin side first at 7 a.m., noon and 5 p.m. Sundays through Saturdays at the following.
- Wisconsin side: Boat launch parking lot on WIS 35 across the street from the wastewater treatment plant, 505 3rd St., Hudson
- Minnesota side: Southwest corner of Hudson Road North and Quinlan Avenue North in Lakeland
- The shuttle won't be operating the weekend of July 4-5.
Sawyer County
County D
- Location: Chippewa River Bridge east of Exeland in the town of Weirgor
- Schedule: March 23 to late July
- Cost: $1.08 million
- Description: Replacing the bridge deck, making concrete surface repairs to the abutments, piers and girders, completing bridge joint, shoulder and guardrail work and replacing the roadway approach pavement
- Traffic impacts: County D is closed at the Chippewa River.
- Traffic is being detoured via WIS 40, WIS 70 and WIS 27.
Sawyer and Price counties
WIS 70
- Location: County GG in the unincorporated community of Loretta in Sawyer County to Pixley Wilderness West Road in the Price County town of Lake west of Fifield
- Schedule: June 15 to early August
- Cost: $5.5 million
- Description of work: Removing a portion of the existing asphalt, repaving the roadway with new asphalt pavement, installing centerline rumble strips, replacing or repairing guardrail as needed, placing gravel along the shoulders and replacing pavement markings
- Traffic impacts: WIS 70 remains open to traffic, but motorists will encounter lane closures controlled by flagging.
Trempealeau County
Smikrud Road
- Location: Grant Creek Bridge south of Ettrick in the town of Gale
- Schedule: Feb. 19 to early July
- Cost: $580,541
- Description: Building a temporary bypass and structure, replacing the bridge, reconstructing roadway approaches and removing the temporary bypass and structure.
- Traffic impacts: None; project complete.
County D
- Location: Elk Creek Bridge northeast of the unincorporated community of Elk Creek
- Schedule: June 10 to mid-September
- Cost: $826,726
- Description of work: Replacing the bridge and roadway approaches and completing shouldering and guardrail work
- Traffic impacts: County D is closed at the bridge.
Regionwide Pavement Marking Project
Various
Location: Barron, Bayfield, Buffalo, Burnett, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, St. Croix, Taylor, Trempealeau and Washburn
Schedule: April 14 to early August
Cost: $2.08 million
Description of work: Replacing pavement markings
Traffic impacts: Motorists will encounter daytime and nighttime lane closures depending on the location of work. Once work resumes Monday, July 6, crews plan to work in the following counties:
- Bayfield County:
- US 2, west of Iron River Bridge to US 63
- Clark County:
- WIS 73, Meridian Avenue to WIS 95
- Douglas County:
- US 53, south of Kent Road to US 2 East
- Dunn County:
- I-94 and southbound WIS 25
- St. Croix County:
- I-94, WIS 65 to Dunn County line
- Taylor County:
- WIS 13, WIS 64 to Medford city limits
- WIS 64, County B to WIS 73 South
Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region: