US 12 (Wisconsin Dells Parkway) scheduled to start early September 2026

Release date: July 23, 2026

Work to reconstruct US 12 (Wisconsin Dells Parkway) between WIS 13 and E Adams Street, Sauk County is set to begin fall 2026. A pre-construction public meeting is scheduled for Monday, July 27, 2026, from 4:30 p.m. to 6:30 p.m. at Frank Fischer Senior Center, 20 Wisconsin Dells Parkway S, Wisconsin Dells. This meeting will go over the project schedule, roadway access and posted detour during construction stages.

The project is designed to improve traffic operations, pavement conditions and pedestrian accommodation along the US 12 project corridor. Some improvements include replacement of pavement, curb and gutter, sidewalk and shared use path on the west side of the roadway between County A and Olympus Road.

Preliminary off-road work started early summer 2026. Project completion is scheduled for spring

2029. The schedule is dependent on favorable weather conditions and construction progress.

During construction, motorists can expect the below impacts on US 12:

  • Major construction operations and long-term lane closures will be restricted to the fall-spring seasons to avoid the summer peak tourist season.
  • One-way traffic will be necessary during fall/spring stages with one lane open in each direction during most other stages.
  • Nighttime (10 p.m. to 6 a.m.) single-lane closures will occur during weeknight (Monday -Thursday) summer months.

For more information regarding traffic impacts, transportation news and improvement project

updates in Wisconsin’s Southwest Region:

Sign up for weekly project updates at:

Wisconsin Dells Parkway (Pilgrim Drive to E. Adams Street) - Sauk County | WisDOT Projects Hub


For more information, contact:

Hannah Hinojos
WisDOT Southwest Region Communication Manager
(608) 246-7907, hannah.hinojos@dot.wi.gov