Release date: September 19, 2025
The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Ashland County
WIS 13
- Location: Butterworth Road to US 2 in Ashland
- Schedule: March 31 to mid-November
- Cost: $9.87 million
- Description: From Butterworth Road to 16th Street: Removing 3¼ inches of existing pavement and overlaying the roadway with 3¼ inches of hot-mix asphalt; replacing deteriorated culverts; and repairing frost heaves. From 16th Street to 6th Street: Replacing the pavement structure with 9 inches of Portland cement concrete pavement, 6 inches of base aggregate, 12 inches of granular subbase and underdrain pipe; replacing storm sewer system, curb ramps, curb and gutter; replacing sidewalk at curb ramps and spot locations; adding a designated bike lane between the travel and parking lanes in each direction on Ellis Avenue; removing and hauling decorative lights to city yard for repainting and reinstalling in landscaped medians; and replacing portions of the city water main in a separate tied project. From 6th Street to US 2: Replacing Portland cement concrete and hot-mix asphalt pavement with 9 inches of Portland concrete cement pavement; extending medians and left-turn lanes, remove one through lane and add designated bike lanes in each direction; and upgrading curb ramps at city street and trail crossings.
- Traffic impacts: WIS 13 is open to traffic, but:
- From 16th Street to US 2: North- and southbound traffic is operating on the southbound lanes.
- The following intersections are closed at WIS 13: 3rd Street East, 6th Street East, 8th Street East, 9th Street East, 11th Street East and 12th Street East.
- Truck traffic is being detoured via WIS 112 and US 2.
WIS 169
- Location: WIS 13 in Mellen to the Iron County line
- Schedule: June 16 to late October
- Cost: $7.1 million
- Description: Removing a portion of the existing pavement, pulverizing the subbase and injecting it with an asphaltic emulsion and then overlaying the roadway with 3.5 inches of new asphalt pavement; replacing the deck on the Bad River Bridge; replacing some culverts and placing new ones; repairing an eroding ditch; removing a railroad crossing, which the railroad will replace later; cleaning culverts and ditches where needed; adding centerline rumble strips; adjusting and/or replacing guardrail; enhancing gravel shoulders; and placing pavement markings.
- Traffic impacts: WIS 169 is closed to through traffic from WIS 13 in Mellen to the Iron County line.
- Through traffic is being detoured via detoured via WIS 13, WIS 77, US 51 and US 2.
- Access to Copper Falls State Park and the North Country National Scenic Trail, as well as local residential traffic, is being maintained using WIS 77 to Olson Road to Butler Road to WIS 169 north of the bridge.
- Temporary traffic control signals have been set up on Butler Road west of East Tyler Avenue to control large noncommercial trailers and campers in the tight curved sections of Butler Road.
Barron County
US 53 South
- Location: Bridges over US 8, 20th Street, Knapp Street, County I, Chetek River, County A, County AA and Carlson School Road between Cameron and New Auburn
- Schedule: May 5 to mid-November, 2025 construction; March 1 to late September, total project completion.
- Cost: $10.91 million
- Description of 2025 work: Replacing the decks on the bridges over County AA and County A; overlaying the decks with concrete on structures over Carlson School Road, Knapp Street and US 8; making miscellaneous repairs to bridges; completing prep work for 2026 construction on the bridges over the Chetek River, County I and 20th Street; and replacing guardrail at the structures.
- Traffic impacts: US 53 South remains open to traffic, but:
- Motorists will encounter lane closures and a reduced speed limit of 60 mph in work zones.
- US 53 South reopens to two lanes of traffic, with a 70-mph speed limit between closures.
- County AA under southbound US 53 southeast of the bridge over County A will be closed from Monday to Monday, September 22-29 for about three days for bridge deck removal.
US 63
- Location: Just west of WIS 48 West to Charrie Lane in Cumberland
- Schedule: April 28 to early October
- Cost: $3.68 million
- Description: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; closing access to the roadway at various locations to improve safety; upgrading pedestrian curb ramps to current Americans With Disabilities Act standards; repairing or replacing curb, gutter and sidewalk; repairing sanitary sewer manholes and storm water inlets as needed; extending the two-way left-turn lane pavement markings between 3rd and 5th avenues; and replacing pavement markings and signage.
- Traffic impacts: US 63 remains open to traffic, but:
- North- and southbound traffic has 12-foot travel lanes through the entire project.
- The shoulder for the northbound lane is closed from the south project limits to the four-way stop until the end of September.
Bayfield County
WIS 13
- Location: Sand River Bridge between Cornucopia and Red Cliff
- Schedule: July 21 to early October
- Cost: $746,767
- Description: Replacing the expansion joints at each end of the bridge deck; removing and replacing the south edge of deck; installing stainless steel protective flashing and corrosion protection on the south edge of deck; replacing the concrete pavement approach slabs; paving approximately 25 feet of asphalt pavement; repairing the concrete surface at the abutments; replacing the south railing; salvaging and cleaning existing rebar; cleaning and painting the steel girder abutment bearings and the south exterior girder and painting the remaining girders at spot locations; sealing the bridge deck; and replacing pavement markings.
- Traffic impacts: The bridge is open to a single lane controlled by temporary traffic signals.
Burnett County
East James Avenue and Johnson Street
- Location: South Robert Street to WIS 70, Grantsburg
- Schedule: July 10 to late August
- Cost: $653,100
- Description: Removing the existing pavement, paving new asphalt pavement, updating sidewalk curb ramps and placing new pavement markings.
- Traffic impacts: Motorists will encounter daytime lane closures controlled by flagging.
Chippewa County
20th Avenue
- Location: Hay Creek Bridge southeast of Cadott
- Schedule: July 21 to early October
- Cost: $558,859
- Description: Replacing the bridge, roadway approach pavement and pavement markings.
- Traffic impacts: The road is closed at the bridge.
County G
- Location: Yellow River Bridge southeast of Cornell
- Schedule: July 8 to late October
- Cost: $1.29 million
- Description: Replacing the bridge, roadway approach pavement and pavement markings.
- Traffic impacts: The road is closed, with a posted detour.
County OO
- Location: Business 53 north of Melby Street to the WIS 124 intersection with Business 53 and County OO in Lake Hallie
- Schedule: August 11 to mid-October
- Cost: $1.72 million
- Description: Removing the existing pavement between Business 53 and Hogarth Street, crushing it down into base material, placing that as road base and paving new asphalt over it; milling off a portion of the existing pavement from Hogarth to the north project limits and placing new asphalt pavement; constructing a segment of trail to tie into the existing trail west of County OO; marking an at-grade trail crossing on County OO at 30th Avenue; installing curb and gutter at various locations; shouldering; and placing new pavement markings.
- Traffic impacts: County OO is open to southbound traffic only from WIS 124 to Business 53.
- Starting at 6 a.m. Monday, Hogarth Street will be closed from BUS 53 to the railroad tracks northwest of County OO from Monday through Wednesday, September 22-24.
- The turn lanes from BUS 53 to Hogarth – the left-turn lane from northbound BUS 53 and the right-turn lane from southbound BUS 53 – also will be closed.
- County OO will remain open to southbound traffic from WIS 124 to BUS 53.
- Southbound traffic will be able to turn left at Hogarth to access southbound BUS 53.
- Northbound County OO traffic will continue to be detoured north on BUS 53 to the County OO/WIS 124 intersection.
- Access to US Bank will be maintained.
- Motorists wanting to get to the bank can follow the signed detour for northbound County OO – BUS 53 to County OO at WIS 124 or Hallie Road, the BUS 53 frontage road, to 110th Street to County OO. Once at Hogarth, motorists can head into the bank parking lot. Following bank business, motorists will turn right onto Hogarth to access BUS 53.
WIS 29
- Location: 50th Avenue interchange and the intersection of 50th Avenue and County J, all in the town of Lafayette east of Chippewa Falls
- Schedule: March 11 to mid-September
- Cost: $5.26 million
- Description: For the WIS 29/50th Avenue interchange project: Removing and replacing the bridge, building retaining walls along east- and westbound WIS 29 at the abutments, replacing the roadway approach pavement and the pavement on the interchange ramps and replacing culverts, guardrail and pavement markings. This project will increase the vertical clearance of the bridge over the highway. For the 50th Avenue/County J intersection project: Constructing a single-lane roundabout, completing approach work on all legs leading into the roundabout, increasing the roadway profile an average of three feet to accommodate the profile rise of the new bridge and replacing storm sewer.
- Traffic impacts: Motorists might encounter lane closures on WIS 29 and shoulder closures on 50th Avenue and County J as contractors complete remaining work.
WIS 124
- Location: Just south of the Duncan Creek Bridge to Bridge Street in Chippewa Falls
- Schedule: June 2 to late October, 2025 construction. Traffic signal work has been pushed to spring 2026 because of utility conflicts on River Street.
- Cost: $2.56 million
- Description: Removing a portion of the existing pavement and placing new asphalt pavement; replacing storm sewer on Elm Street; modifying traffic signals at Columbia Street, Grand Avenue, Central Street, Spring Street and River Street; and updating sidewalk curb ramps.
- Traffic impacts: None.
US 53
- Location: 40th Avenue in Lake Hallie to County B in the town of Tilden
- Schedule: March 10 to late October, 2025 construction; and April 1, 2024, to late June 2026, overall project
- Cost: $36.6 million
- Description of 2025 work: Replacing the pavement on northbound US 53 and constructing temporary emergency pullouts south of County N; making repairs and completing polymer overlays on the northbound US 53 bridges over the Chippewa River and Business 29/County X; replacing the pavement on the on- and off-ramps at the County B and Business 29/County X interchanges; replacing the pavement on southbound US 53 north of County N, including the north- and southbound passing lanes north of County B; milling and overlaying the shoulder between County B and County Q along the driving lane of southbound US 53; replacing guardrail; completing culvert work; and installing new pavement markings and shoulder rumble strips.
- Traffic impacts: US 53 remains open to traffic, but:
- A single lane in both directions is operating on northbound US 53 from County N to County
- The ramp from County B to southbound US 53 is closed until late October.
- The ramp from southbound US 53 to County B is expected to be closed to traffic from Tuesday, September 16 to late October.
- The speed limit is reduced to 55 mph in the work zone.
Chippewa and Eau Claire counties
US 53
- Location: Golf Road in Eau Claire to 40th Avenue in Lake Hallie
- Schedule: June 2 to late October
- Cost: $10 million
- Description: Making repairs to or removing and replacing segments of concrete pavement; overlaying southbound US 53 with asphalt from WIS 312 (North Crossing) in Eau Claire to County OO in Lake Hallie; completing work at various structures; replacing guardrail; and placing new pavement markings.
- Traffic impacts: US 53 remains open to traffic, but motorists will encounter ramp and lane closures.
- Motorists will encounter ramp and lane closures during off-peak travel hours.
- Most work is being completed at night, but some will occur during daytime hours.
- The following overnight ramp and lane closures are planned but dependent on weather:
- Tonight: Ramp from WIS 312 (North Crossing) to southbound US 53. The right (outside) lane on southbound US 53 also will be closed in this area.
- Traffic will be detoured via WIS 312 to northbound US 53 to Melby Street to southbound US 53.
- Saturday, September 20: Ramp from eastbound WIS 29 to the southbound US 53 outside lane and ramp from County OO to southbound US 53
- Traffic for the former will be detoured via northbound US 53 to westbound WIS 29 to southbound US 53.
- Traffic for the latter will be detoured via BUS 53 to Melby Street to southbound US 53.
Chippewa, Eau Claire and St. Croix counties
WIS 29, US 53 and I-94
- Location: WIS 29: 40th Avenue to 50th Avenue, Lake Hallie, County J to 190th Street, town of Lafayette, and County G, town of Delmar, to 0.45 mile west of County H in Stanley; US 53, County QQ, town of Seymour, to La Salle Street, Eau Claire; and I-94, 0.95 mile west of WIS 65 to WIS 65, Roberts, and 140th Street, town of Kinnickinnic, to County J, town of Pleasant Valley
- Schedule: August 7 to early November
- Cost: $2.99 million
- Description: Installing median cable barrier, reconstructing drainage structures, grading, restoring the graded areas and placing shoulder aggregate.
- Traffic impacts: Crews are working on I-94 in St. Croix County and are expected to return to US 53 in Eau Claire County next week.
- In St. Croix County, motorists will encounter inside lane closures in I-94 from 140th Street to County J from 8 tonight to 9 a.m. Saturday.
- Starting Monday, September 22:
- In Eau Claire County, motorists will encounter inside lane closures on US 53 from 7 p.m. to 7 a.m. Monday through Friday, September 26 from County QQ to La Salle Street.
- Motorists will encounter shoulder closures when lane closures are removed.
- In St. Croix County, motorists will encounter inside lane closures on I-94 from the WIS 65 overpass to one mile west of WIS 65 Monday through Saturday, September 27.
- Lane closures on eastbound I-94 will typically be from 7 p.m. to 1 p.m. Monday through Wednesday and 8 p.m. to 9 a.m. Thursday through Saturday.
- Lane closures on westbound I-94 will typically be from 6 p.m. to 6 a.m.
- Motorists will encounter shoulder closures when lane closures are removed.
Clark County
Main Street
- Location: East Fork Halls Creek Bridge in Humbird
- Schedule: August 26 to mid-October
- Cost: $399,999
- Description: Removing and replacing the bridge and reconstructing the bridge approaches.
- Traffic Impacts: The road is closed at the bridge.
Pine Road
- Location: Goggle-Eye Creek Bridge northwest of Thorp
- Schedule: August 25 to mid-October
- Cost: $399,999
- Description: Removing and replacing the bridge and reconstructing the roadway approaches.
- Traffic Impacts: The road is closed at the bridge.
County G
- Location: Black River Bridge in Greenwood
- Schedule: June 2 to late November
- Cost: $3.8 million
- Description: Removing and replacing the bridge, reconstructing the bridge approaches and installing new guardrail and wider shoulders.
- Traffic impacts: County G is closed.
- Traffic is being detoured via WIS 73, County OO and County O.
WIS 29
- Location: Koser Avenue west of Thorp to County D in Owen
- Schedule: May 1 to mid-October
- Cost: $23.74 million
- Description: Making repairs to the concrete pavement; placing 3.75 inches of new asphalt pavement over WIS 29; removing 1.25 inches of the existing pavement on the ramps at the WIS 29 interchanges at WIS 73 North/County M and WIS 73 South/County T and placing 2.25 inches of new asphalt; replacing the expansion joints on the east- and westbound WIS 29 bridges over the Black River west of Withee; replacing all wing walls on a culvert carrying the Popple River under WIS 29 west of County D in Owen; replacing the northwest wing wall on a culvert between Thorp and Withee; cleaning culverts and ditches; and replacing guardrail and pavement markings.
- Traffic impacts: WIS 29 remains open to traffic, but motorists will encounter a speed reduction during work hours in active work areas and the following on:
- Eastbound WIS 29:
- Single-lane closures from WIS 73/County M interchange to Sterling Avenue and County O to County D
- Westbound WIS 29:
- Single-lane closure from Koser Avenue to WIS 73 North/County M, Gorman Avenue to County O and the WIS 73 South/County T interchange to County D
- WIS 73 North/County M interchange (Exit 108, Thorp)
- Motorists on County M will be directed by flaggers for miscellaneous work.
- WIS 73 South/County T interchange (Exit 118, Withee, Greenwood and Neillsville)
- Motorists will encounter lane closures controlled by temporary traffic signals to facilitate work on WIS 73 South.
- Side roads:
- Motorists will be directed by flaggers when paving through side road intersections in both directions on WIS 29.
WIS 73
- Location: Rock Creek Bridge in Greenwood to WIS 29 East south of Withee
- Schedule: April 25 to late September
- Cost: $8.29 million
- Description: From Rock Creek Bridge to West Hunt Street in Greenwood: Removing 3.25 inches of existing asphalt and placing 3.25 inches of new asphalt pavement; replacing curb ramps and making spot curb and gutter repairs; replacing guardrail; and placing pavement markings. From West Hunt Street north to WIS 29 East: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; replacing cattle passes no longer in use with culvert pipes; extending a box culvert north of Greenwood and replacing the structure’s wing walls; overlaying the Popple River Bridge deck with concrete, repairing the concrete surface on the bridge abutments, replacing two wing walls and repairing scour; cleaning or replacing culverts; cleaning ditches; and replacing or adjusting guardrail.
- Traffic impacts: Motorists will encounter lane closures controlled by flagging as finishing work is completed.
Douglas County
Lidberg Bridge Road
- Location: Eau Claire River Bridge east of Gordon
- Schedule: June 9 to mid-September
- Cost: $622,116
- Description: Replacing the bridge.
- Traffic impacts: None; project complete.
Hammond Avenue
- Location: North 21st Street to North 28th Street, city of Superior
- Schedule: May 5 to late October
- Cost: $4.49 million
- Description: Replacing the pavement, base and subbase materials; installing subbase drainage; replacing sewer and water utilities; replacing curb, gutter and sidewalk; constructing a median between the two traffic lanes; building a bicycle trail; and placing pavement markings and signage.
- Traffic impacts: The road is closed in the work zone.
County C
- Location: Minnesota state line to Barnes Road southwest of the village of Oliver
- Schedule: May 19 to early October, 2025 construction; October 16, 2024 to early October 2025, overall project
- Cost: $5.1 million
- Description of 2025 work: Reconstructing the existing roadway with new asphalt, making railroad crossing improvements, realigning the County C/W intersection and installing pavement markings.
- Traffic impacts: County C is closed; a signed detour is in place.
US 2
- Location: Bong Bridge connecting Superior and Duluth, MN
- Schedule: August 6 to early December
- Cost: $6.38 million
- Description: Painting spot locations of the existing steel arch structure of the center span; making concrete surface repairs at spot locations of the two piers that support the center steel arch structure; removing and replacing three rubber strip seals of the center tied arch; replacing street lighting on the Minnesota half of the structure, including on the Minnesota ramps; replacing street lighting on the Wisconsin approach; applying a concrete sealer to the entire deck, including the Minnesota ramps; and placing new pavement markings on the entire bridge, Minnesota ramps and Wisconsin approach.
- Traffic impacts: US 2 remains open to traffic, but the outside lane and shoulder are closed in both directions.
US 53
- Location: 2nd Avenue East to Hughitt Avenue in Superior
- Schedule: July 14 to mid-September
- Cost: $3.98 million
- Description: For the road rehabilitation project: Milling 1.5 inches off the roadway between Hughitt Avenue and the bridge over the railroad tracks and overlaying the driving lanes with a 1.5-inch layer of asphalt; milling the existing asphalt pavement down to the concrete pavement between the bridge over the railroad tracks and 2nd Avenue East, making spot repairs to the underlying concrete and then placing 3 inches of new asphalt pavement; making spot curb and gutter repairs; repairing various inlets and storm and sanitary sewer manholes; upgrading or installing curb ramps at pedestrian crossings. For the safety project: Closing the existing median on US 53 at E Street; adding new turn bays on US 53 to for motorists turning right onto E Street; widening Lenroot Drive, currently a one-way street, to accommodate two-lane, two-way traffic; making improvements at the intersection of Lenroot Drive and Winter Street; and milling the existing pavement on Lenroot Drive, Winter Street and East 1st Street and then overlaying the roads with asphalt.
- Traffic impacts: US 53 remains open to traffic, but:
- Motorists will encounter lane closures and a 10-foot width restriction.
- The on- and off-ramps on the Blatnik Bridge are expected to be milled and paved Wednesday to Friday, September 24-26. The work will result in closure of the ramp being worked on and short-term detours.
Dunn County
US 12
- Location: I-94 to WIS 25, including the intersection of US 12, WIS 25 and Pine Avenue East in the city of Menomonie
- Schedule: May 19 to mid-September
- Cost: $1.73 million
- Description: Milling off part of the existing pavement on US 12 and placing new asphalt pavement; realigning the left-turn lanes on all approaches to the intersection to improve motorists’ visibility; realigning the eastbound right-turn lane on US 12 to southbound WIS 25 North to improve the viewing angle for drivers and the southbound right-turn lane on WIS 25 North to US 12 to improve truck turning movements; installing monotube traffic signal equipment at the intersection to increase signal head visibility; constructing a raised median along US 12; replacing the concrete on US 12 on the west leg of the intersection; milling and overlaying Pine Avenue East on the east leg of the intersection; updating sidewalk curb ramps; placing new pavement markings; and replacing signage.
- Traffic impacts: None; project complete.
Eau Claire County
Various
- Location: Multiple bus stops in the city of Eau Claire
- Schedule: August 18 to late September
- Cost: $262,881Description: Adding two concrete pads connecting sidewalk to back of curb and replacing existing sidewalk at multiple bus stop locations.
- Traffic impacts: At work sites, motorists will encounter shoulder closures, and pedestrians will encounter sidewalk closures.
- For the week of September 22, crews will:
- Begin work at Bellevue Avenue and Spring Street; Birch and Germania streets; Keystone Crossing and Bullis Farm Road; Craig Road at Oak Ridge Drive and the Marshfield Medical Center-Eau Claire entrance; Vine Street at 7th Street and Florence Avenue; El Dorado Boulevard and Imperial Circle; West MacArthur Avenue and Ruth Street; Sunset Drive and Fairmont Avenue; and Oakwood Hills Parkway at Manny’s Cocina.
- Pour concrete at Truax Boulevard at Garden Street and Jeffers Road; Runway Avenue and Robin Road; Starr Avenue and North Lane; and Platt and 2nd streets and complete restoration at those locations and at West Hamilton Avenue and El Dorado Boulevard; Vine and Warden streets; Meridian Heights and Crestview drives; and Westover Road and Ellis Street.
WIS 93
- Location: Cedar Road south of Eau Claire to the Trempealeau County line north of Eleva
- Schedule: May 19 to late September
- Cost: $7.7 million
- Description: Milling 3.25 inches of the existing asphalt surface and overlaying the road with 3.25 inches of new asphalt; replacing the Clear Creek Bridge and box culvert at Pine Creek with bridges; cleaning, replacing and resetting sections of existing culverts in the project limits; widening WIS 93’s paved shoulders to five feet; installing new pavement markings and shoulder rumble strips; adding asphaltic curbs/flumes to manage roadway runoff; and replacing or adjusting guardrail.
- Traffic impacts: Motorists will encounter lane and shoulder closures as finishing work is completed.
US 12
- Location: Industrial Drive in Altoona to the Fall Creek Bridge
- Schedule: August 11 to November
- Cost: $4.48 million
- Description: Milling and resurfacing the existing pavement with new asphalt; widening paved shoulders from 3 feet to 5 feet; installing shoulder and centerline rumble strips to enhance driver safety; repairing or replacing aging culverts and cattle passes; upgrading guardrail throughout the project; improving drainage by grading ditches south of US 12 near Schultz Road and west of Oak Knoll Road; installing new pavement markings throughout the corridor; and clearing trees from a 500-foot segment between Voight and Oak Knoll roads.
- Traffic impacts: Motorists will encounter single-lane closures controlled by flagging with a 19-foot width restriction controlled by flagging where crews are paving.
I-94
- Location: US 53 interchange to Mallard Road southwest of Eau Claire
- Schedule: March 17 and mid-November, 2025 construction; and March 4, 2024, to November 2026, overall project
- Cost: $69.9 million
- Description of 2025 work: Replacing the pavement of westbound I-94 from Otter Creek to Mallard Road, the westbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under westbound I-94 near County D.
- Traffic impacts: I-94 is open to traffic, but:
- Motorists will encounter single-lane closures during nonpeak travel hours and a 60-mph speed limit in both directions.
- The speed limit in both directions is 60 mph.
- County D is closed at I-94.
Jackson County
County N
- Location: County C to Rabbit Run Road
- Schedule: April 2 to mid-October
- Cost: $3.85 million
- Description: Replacing the pavement on an approximate 1.23-mile stretch; pulverizing and relaying the existing pavement on a 4.15-mile segment and placing new asphalt pavement; and replacing guardrail, pavement markings and signage.
- Traffic impacts: County N is closed in the project limits.
WIS 54
- Location: Wilson and Mill Creek bridges west of Melrose
- Schedule: June 23 to late November
- Cost: $2.79 million
- Description: Removing and replacing both bridges and replacing the pavement on both sides of each structure, guardrail and pavement markings.
- Traffic impacts: WIS 54 is:
- Closed at Wilson Creek; traffic is being detoured via US 53/WIS 93, I-90, WIS 16, WIS 108 and WIS 71.
- Open at Mill Creek through use of a temporary bypass controlled by temporary traffic signals.
I-94
- Location: Bridges over the Black River in the city of Black River Falls and the Union Pacific railroad tracks in the town of Brockway
- Schedule: February 24 to late May, bridge construction, and September 9 to mid-October, crossover removal, 2025 construction; and September 5, 2023 to October 2025, overall project
- Cost: $5.2 million
- Description of 2025 work: Overlaying the eastbound bridge decks with concrete; repainting each structure’s girders; replacing their expansion joints, wing walls, approach pavement and guardrail; placing new pavement markings; and removing median crossovers.
- Traffic impacts: Motorists will encounter inside lane closures in both directions Mondays through Fridays as crossovers near both bridges are removed.
Pepin County
County D
- Location: Eau Galle River Bridge northeast of Arkansaw
- Schedule: June 11 to mid-September
- Cost: $913,094
- Description: Replacing the bridge, pavement on both sides of the structure, signage and pavement markings.
- Traffic impacts: None; project complete.
County PP
- Location: South county line to V Schuh Lane south of Durand
- Schedule: July 21 to early October
- Cost: $1.13 million
- Description: Replacing the asphalt pavement, realigning a segment of the highway, replacing cross culverts and guardrail, improving shoulders and placing pavement markings and signage.
- Traffic impacts: The road is closed between the project limits.
WIS 35
- Location: Walnut Street in Stockholm to the Pierce County line
- Schedule: August 25 to early November
- Cost: $4.28 million
- Description: Removing 2.25 inches of existing pavement, paving 3.75 inches of new asphalt pavement, completing culvert work, replacing guardrail and placing new pavement markings.
- Traffic impacts: Motorists will encounter daytime lane closures controlled by flagging.
Pierce County
1005th Street
- Location: Wind River Bridge in the town of Diamond Bluff southeast of Prescott
- Schedule: September 16 to mid-November
- Cost: $540,271
- Description: Replacing the bridge, realigning the stream, placing riprap and completing approach work, including asphalt paving.
- Traffic Impacts: The road is closed on each end at WIS 35.
US 63
- Location: US 10 east of Ellsworth to WIS 29 East
- Schedule: May 5 to early October
- Cost: $8.5 million
- Description: Removing 1.25 inches of the existing pavement and place 3.25 inches of new asphalt pavement; replacing the decks on the bridges carrying US 63 over the south fork of Lost Creek, Lost Creek and a branch of the Rush River; replacing culverts, gravel shoulders and guardrail; cleaning ditches; and placing new pavement markings.
- Traffic impacts: Motorists will encounter daytime single-lane closures controlled by flagging.
US 63
- Location: Minnesota state line to US 10 west of Ellsworth
- Schedule: June 30 to late September
- Cost: $7.1 million
- Description: Removing 3.75 inches of the existing pavement and placing 3.75 inches of new asphalt; adding rumble strips; adjusting guardrail; completing culvert maintenance; and installing permanent pavement markings.
- Traffic impacts: Motorists will encounter daytime single-lane closures controlled by flagging and shoulder closures.
St. Croix County
WIS 35
- Location: South of I-94 between Stageline Road and Hanley Road/High Ridge Drive in Hudson
- Schedule: August 20 to mid-September
- Cost: $3.57 million
- Description: Extending an existing noise wall on the west side of WIS 35 south of the existing noise wall between the highway and Heritage Boulevard and adding two noise walls on the east side of WIS 35 - one southwest of Meadows Park and northwest of the Canary Way cul-de-sac and the other between the highway and Meadowlark Drive and Meadowlark Lane.
- Traffic impacts: Motorists will encounter the following impacts:
- The right lane and shoulder on northbound WIS 35 are closed just south of the Hanley Road/High Ridge Drive overpass to the exit direction signs.
- The auxiliary turn lanes from High Ridge Drive to the ramp to northbound WIS 35 and the ramp from southbound WIS 35 to Hanley Road are closed.
- The right lane on northbound WIS 35 will be closed starting at 7 a.m. Monday, September 22 and come down by 6 p.m. Friday, September 26.
US 63
- Location: Bridge carrying US 63 over a branch of the Rush River in Baldwin and Spruce Street intersection
- Schedule: April 14 to September
- Cost: $2.34 million
- Description: Replacing the bridge, widening the east side of US 63 north of the bridge and shift the Spruce Street intersection to the east, converting the current northbound US 63 lane into a turn lane for southbound US 63 traffic to turn onto Spruce, constructing a new northbound US 63 lane east of the new turn lane and replacing the culvert under Spruce Street, pavement markings and signage.
- Traffic impacts: None; project complete.
US 63
- Location: Bridge carrying a branch of the Willow River east of New Richmond
- Schedule: August 25 to late October
- Cost: $442,677
- Description: Replacing the bridge deck, repairing spalling on bridge abutments and exposed rebar on girders, replacing concrete approach slabs and up to 50 feet of the approaching road on both sides of the bridge, reinstalling guardrail and replacing pavement markings.
- Traffic Impacts: US 63 is closed on both sides of the bridge.
- Traffic is being detoured via US 63, WIS 46 and US 8.
I-94
- Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson
- Schedule: March 17 to mid-October, 2025 construction; and September 9, 2024 to mid-October 2026, overall project
- Cost: $20.08 million
- Description of 2025 work: Removing and replacing the westbound bridges and 1,000 to 1,200 feet of the I-94 pavement on both sides of structures in both directions; installing storm sewer; and replacing guardrail and pavement markings.
- Traffic impacts: I-94 remains open to traffic, but:
- Traffic on westbound I-94 is operating on temporary lanes built in the median near the 100th Street and Kinney Road bridges.
- The speed limit is reduced to 60 mph for traffic operating on the temporary lanes.
- Motorists will encounter single-lane closures on the westbound lanes from 6 p.m. to 6 a.m. Monday to Saturday, September 22-27 as crews pave I-94.
- Traffic could be switched to the newly constructed permanent westbound lanes at the end of next week or the week of September 29.
Sawyer County
County B
- Location: 2nd Street to West Chippewa Trail
- Schedule: August 8 to early October
- Cost: $807,337
- Description: Removing a portion of the existing pavement, placing new asphalt pavement, replacing concrete curb and gutter at spot locations, improving curb ramps and installing new pavement markings.
- Traffic impacts: One lane of County B in each direction will remain open.
County CC
- Location: Bridge over the Chippewa Flowage southwest of New Post
- Schedule: September 8 to early November
- Cost: $613,953
- Description: Replacing the bridge deck, making abutment repairs, replacing approach pavement, placing riprap and replacing guardrail.
- Traffic Impacts: The road is closed at the bridge.
Taylor County
9th Street
- Location: Eastview Drive to East Broadway Avenue in Medford
- Schedule: August 25 to mid-October
- Cost: $292,455
- Description: Pulverizing the existing pavement, removing 4 inches of ground material, paving 4 inches of new asphalt and replacing curb and gutter.
- Traffic Impacts: The road is closed.
Elm Avenue and Robin Drive
- Location: Deer Creek culverts on Elm Avenue and Robin Drive and West Branch Big Eau Pleine River Bridge on Elm, all southeast of Stetsonville
- Schedule: May 27 to mid-November
- Cost: $1.75 million
- Description: At Deer Creek culverts on Elm Avenue and Robin Drive: Removing the culvert pipes, replacing them with bridges, reconstructing 50 feet of roadway on both sides of the new structures, completing grading and placing riprap between the abutments and stream edges. In addition, realigning the stream at Deer Creek on Robin Drive. At West Branch Big Eau Pleine River: Replacing the existing bridge and reconstructing 100 feet of approach roadway.
- Traffic impacts: Elm Avenue is closed.
State Road
- Location: Little Rib River Bridge in village of Rib Lake
- Schedule: August 7 to early October
- Cost: $602,613
- Description: Replacing the bridge and approach pavement.
- Traffic impacts: The road is closed.
Trempealeau County
US 10
- Location: Nelson Road to I-94 westbound ramps in Osseo
- Schedule: April 14 to late September
- Cost: $5.78 million
- Description: Removing the pavement from east of the Buffalo River State Park Trail to just west of Rose Lane and placing 8.5 inches of concrete pavement along with six inches of underlying base aggregate; repairing or replacing existing concrete pavement near I-94 at spot locations; making concrete surface repairs on the bridge over the north fork of the Buffalo River and overlaying the deck with concrete; replacing storm sewer, sanitary sewer and water main; and replacing sidewalk, curb ramps, curb and gutter and pavement markings.
- Traffic impacts: US 10 is closed to through traffic from County K to Rose Lane.
- Through traffic on US 10 is being detoured via US 53, County HH and I-94.
- Through traffic on US 53, where it runs concurrent with US 10 between its northern and southern legs, is being detoured via WIS 121, County HH and I-94.
- A minimum of two side roads in the work zone are open for north and south traffic.
- Access is being maintained to businesses and residences in the work zone.
Washburn County
County K
- Location: US 63 in the city of Spooner to Sunset Lane
- Schedule: June 2 to late August
- Cost: $2.01 million
- Description: From US 63 to division Street: Removing and replacing the existing pavement and base course, replacing curb and gutter, making spot sanitary sewer improvements, completing storm sewer repairs and placing new pavement markings and signage. From division Street to Sunset Lane: Pulverizing the existing pavement and repaving it.
- Traffic impacts: County K is open to traffic, but finishing work might result in lane closures controlled by flagging.
Regionwide Pavement Marking Project
Various
- Location: In Northwest Region: Barron, Bayfield, Buffalo, Clark, Dunn, Jackson, Pierce, St. Croix, Sawyer, Polk, Trempealeau and Washburn counties. In Southwest Region: Juneau and Monroe counties
- Schedule: April 28 to mid-October
- Cost: $1.97 million
- Description: Replacing epoxy centerlines, edge lines and special markings.
- Traffic impacts: Motorists will encounter moving lane closures or traffic diversions where crews are working. For the coming week, crews are anticipated to:
- Complete work on a segment of I-94 in St. Croix County
- Continue work on segments of US 63 in Bayfield, Sawyer and Washburn counties
- Begin work on a segment of US 8 in Polk county
Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region: