WisDOT Northwest Region Construction Update - October 24

Release date: October 24, 2025

The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.

Ashland County

WIS 13
  • Location: Butterworth Road to US 2 in Ashland
  • Schedule: March 31 to mid-November
  • Cost: $9.87 million
  • Description: From Butterworth Road to 16th Street: Removing 3¼ inches of existing pavement and overlaying the roadway with 3¼ inches of hot-mix asphalt; replacing deteriorated culverts; and repairing frost heaves. From 16th Street to 6th Street: Replacing the pavement structure with 9 inches of Portland cement concrete pavement, 6 inches of base aggregate, 12 inches of granular subbase and underdrain pipe; replacing storm sewer system, curb ramps, curb and gutter; replacing sidewalk at curb ramps and spot locations; adding a designated bike lane between the travel and parking lanes in each direction on Ellis Avenue; removing and hauling decorative lights to city yard for repainting and reinstalling in landscaped medians; and replacing portions of the city water main in a separate tied project. From 6th Street to US 2: Replacing Portland cement concrete and hot-mix asphalt pavement with 9 inches of Portland concrete cement pavement; extending medians and left-turn lanes, remove one through lane and add designated bike lanes in each direction; and upgrading curb ramps at city street and trail crossings.
  • Traffic impacts: WIS 13 is open to traffic, but:
    • From 16th Street to 5th Street, north- and southbound traffic is operating on the southbound lanes.
    • From 5th Street to US 2, traffic is operating in the parking lanes on the north- and southbound lanes.
    • The following intersections are closed at WIS 13: 7th Street East, 8th Street East, 9th Street East, 11th Street East and 12th Street East.
    • Truck traffic is being detoured via WIS 112 and US 2.
WIS 169
  • Location: WIS 13 in Mellen to the Iron County line
  • Schedule: June 16 to late October
  • Cost: $7.1 million
  • Description: Removing a portion of the existing pavement, pulverizing the subbase and injecting it with an asphaltic emulsion and then overlaying the roadway with 3.5 inches of new asphalt pavement; replacing the deck on the Bad River Bridge; replacing some culverts and placing new ones; repairing an eroding ditch; removing a railroad crossing, which the railroad will replace later; cleaning culverts and ditches where needed; adding centerline rumble strips; adjusting and/or replacing guardrail; enhancing gravel shoulders; and placing pavement markings.
  • Traffic impacts: Motorists will encounter lane closures controlled by flagging as finishing work is completed.

Barron County

14 1/2 Avenue
  • Location: Barker Creek Bridge northwest of Cameron
  • Schedule: September 29 to late November
  • Cost: $482,782
  • Description: Replacing the bridge, approach pavement and signs.
  • Traffic impacts: The road is closed at the bridge.
US 53 South
  • Location: Bridges over US 8, 20th Street, Knapp Street, County I, Chetek River, County A, County AA and Carlson School Road between Cameron and New Auburn
  • Schedule: May 5 to mid-November, 2025 construction; March 1 to late September, total project completion.
  • Cost: $10.91 million
  • Description of 2025 work: Replacing the decks on the bridges over County AA and County A; overlaying the decks with concrete on structures over Carlson School Road, Knapp Street and US 8; making miscellaneous repairs to bridges; completing prep work for 2026 construction on the bridges over the Chetek River, County I and 20th Street; and replacing guardrail at the structures.
  • Traffic impacts: US 53 South remains open to traffic, but:
    • Motorists will encounter lane closures and a reduced speed limit of 60 mph in work zones.
    • US 53 South reopens to two lanes of traffic, with a 70-mph speed limit between closures.
    • There is a maximum width of 15 feet 3 inches on the open lane on most bridges.
    • Motorists on US 8 will encounter single-lane closures until about 4 p.m. today.
US 63
  • Location: Just west of WIS 48 West to Charrie Lane in Cumberland
  • Schedule: April 28 to mid-October
  • Cost: $3.68 million
  • Description: Removing 3.25 inches of the existing pavement and placing 3.25 inches of new asphalt pavement; closing access to the roadway at various locations to improve safety; upgrading pedestrian curb ramps to current Americans With Disabilities Act standards; repairing or replacing curb, gutter and sidewalk; repairing sanitary sewer manholes and storm water inlets as needed; extending the two-way left-turn lane pavement markings between 3rd and 5th avenues; and replacing pavement markings and signage.
  • Traffic impacts: None are anticipated as finishing work is completed.

Bayfield County

WIS 13
  • Location: Sand River Bridge between Cornucopia and Red Cliff
  • Schedule: July 21 to mid-October
  • Cost: $746,767
  • Description: Replacing the expansion joints at each end of the bridge deck; removing and replacing the south edge of deck; installing stainless steel protective flashing and corrosion protection on the south edge of deck; replacing the concrete pavement approach slabs; paving approximately 25 feet of asphalt pavement; repairing the concrete surface at the abutments; replacing the south railing; salvaging and cleaning existing rebar; cleaning and painting the steel girder abutment bearings and the south exterior girder and painting the remaining girders at spot locations; sealing the bridge deck; and replacing pavement markings.
  • Traffic impacts: None; project complete.

Burnett County

Burnikel Road
  • Location: Clam River Bridge
  • Schedule: September 22 to early November
  • Cost: $530,913
  • Description: Replacing the bridge and reconstructing 100 feet of approach roadway.
  • Traffic Impacts: The road is closed at the bridge.

Chippewa County

370th Street
  • Location: Bridge over a branch of the Wolf River south of Stanley
  • Schedule: October 6 through mid-November
  • Cost: $423,070
  • Description: Replacing the bridge and roadway approach pavement and placing riprap.
  • Traffic impacts: The road is closed at the bridge.
County G
  • Location: Yellow River Bridge southeast of Cornell
  • Schedule: July 8 to late October
  • Cost: $1.29 million
  • Description: Replacing the bridge, roadway approach pavement and pavement markings.
  • Traffic impacts: The road is closed, with a posted detour.
County OO
  • Location: Business 53 north of Melby Street to the WIS 124 intersection with Business 53 and County OO in Lake Hallie
  • Schedule: August 11 to mid-October
  • Cost: $1.72 million
  • Description: Removing the existing pavement between Business 53 and Hogarth Street, crushing it down into base material, placing that as road base and paving new asphalt over it; milling off a portion of the existing pavement from Hogarth to the north project limits and placing new asphalt pavement; constructing a segment of trail to tie into the existing trail west of County OO; marking an at-grade trail crossing on County OO at 30th Avenue; installing curb and gutter at various locations; shouldering; and placing new pavement markings.
  • Traffic impacts: None; project complete.
WIS 124
  • Location: Just south of the Duncan Creek Bridge to Bridge Street in Chippewa Falls
  • Schedule: June 2 to late October, 2025 construction. Traffic signal work has been pushed to spring 2026 because of utility conflicts on River Street.
  • Cost: $2.56 million
  • Description: Removing a portion of the existing pavement and placing new asphalt pavement; replacing storm sewer on Elm Street; modifying traffic signals at Columbia Street, Grand Avenue, Central Street, Spring Street and River Street; and updating sidewalk curb ramps.
  • Traffic impacts: Motorists might encounter lane closures on side streets as minor 2025 work is completed.
US 53
  • Location: 40th Avenue in Lake Hallie to County B in the town of Tilden
  • Schedule: March 10 to late October, 2025 construction; and April 1, 2024 to late June 2026, overall project
  • Cost: $36.6 million
  • Description of 2025 work: Replacing the pavement on northbound US 53 and constructing temporary emergency pullouts south of County N; making repairs and completing polymer overlays on the northbound US 53 bridges over the Chippewa River and Business 29/County X; replacing the pavement on the on- and off-ramps at the County B and Business 29/County X interchanges; replacing the pavement on southbound US 53 north of County N, including the north- and southbound passing lanes north of County B; milling and overlaying the shoulder between County B and County Q along the driving lane of southbound US 53; replacing guardrail; completing culvert work; and installing new pavement markings and shoulder rumble strips.
  • Traffic impacts: US 53 remains open to traffic, but:
    • A single lane in both directions is operating on northbound US 53 from County N to County
    • The ramps from southbound US 53 to County B and County B to southbound US 53 is closed until late October.
    • The speed limit is reduced to 55 mph in the work zone.

Chippewa and Eau Claire counties

US 53
  • Location: Golf Road in Eau Claire to 40th Avenue in Lake Hallie
  • Schedule: June 2 to late October
  • Cost: $10 million
  • Description: Making repairs to or removing and replacing segments of concrete pavement; overlaying southbound US 53 with asphalt from WIS 312 (North Crossing) in Eau Claire to County OO in Lake Hallie; completing work at various structures; replacing guardrail; and placing new pavement markings.
  • Traffic impacts: US 53 remains open to traffic, but:
    • Most work is being completed at night, but some work will occur during daytime hours.
    • Motorists will encounter ramp and lane closures during off-peak travel hours.

Clark County

Pine Road
  • Location: Goggle-Eye Creek Bridge northwest of Thorp
  • Schedule: August 25 to mid-October
  • Cost: $399,999
  • Description: Removing and replacing the bridge and reconstructing the roadway approaches.
  • Traffic Impacts: The road is closed at the bridge.
County G
  • Location: Black River Bridge in Greenwood
  • Schedule: June 2 to late November
  • Cost: $3.8 million
  • Description: Removing and replacing the bridge, reconstructing the bridge approaches and installing new guardrail and wider shoulders.
  • Traffic impacts: County G is closed.
    • Traffic is being detoured via WIS 73, County OO and County O.
WIS 29
  • Location: Koser Avenue west of Thorp to County D in Owen
  • Schedule: May 1 to mid-November
  • Cost: $23.74 million
  • Description: Making repairs to the concrete pavement; placing 3.75 inches of new asphalt pavement over WIS 29; removing 1.25 inches of the existing pavement on the ramps at the WIS 29 interchanges at WIS 73 North/County M and WIS 73 South/County T and placing 2.25 inches of new asphalt; replacing the expansion joints on the east- and westbound WIS 29 bridges over the Black River west of Withee; replacing all wing walls on a culvert carrying the Popple River under WIS 29 west of County D in Owen; replacing the northwest wing wall on a culvert between Thorp and Withee; cleaning culverts and ditches; and replacing guardrail and pavement markings.
  • Traffic impacts: WIS 29 remains open to traffic, but:
    • Motorists will encounter single-lane closures in both directions between Koser Avenue and County D and a speed reduction to 55 mph during work hours in active work areas.
    • WIS 73 North/County M interchange (Exit 108, Thorp): Motorists on County M will be directed by flaggers for miscellaneous work.
    • WIS 73 South/County T interchange (Exit 118, Withee, Greenwood and Neillsville): Motorists on County T will be directed by flaggers for miscellaneous work.
    • Side roads: Motorists will be directed with flaggers when paving through side road intersections in both directions on WIS 29.

Douglas County

Hammond Avenue
  • Location: North 21st Street to North 28th Street, city of Superior
  • Schedule: May 5 to late October
  • Cost: $4.49 million
  • Description: Replacing the pavement, base and subbase materials; installing subbase drainage; replacing sewer and water utilities; replacing curb, gutter and sidewalk; constructing a median between the two traffic lanes; building a bicycle trail; and placing pavement markings and signage.
  • Traffic impacts: The road is closed in the work zone.
County C
  • Location: Minnesota state line to Barnes Road southwest of the village of Oliver
  • Schedule: May 19 to early October, 2025 construction; October 16, 2024 to early October 2025, overall project
  • Cost: $5.1 million
  • Description of 2025 work: Reconstructing the existing roadway with new asphalt, making railroad crossing improvements, realigning the County C/W intersection and installing pavement markings.
  • Traffic impacts: None; project complete.
US 2
  • Location: Bong Bridge connecting Superior and Duluth, MN
  • Schedule: August 6 to early December
  • Cost: $6.38 million
  • Description: Painting spot locations of the existing steel arch structure of the center span; making concrete surface repairs at spot locations of the two piers that support the center steel arch structure; removing and replacing three rubber strip seals of the center tied arch; replacing street lighting on the Minnesota half of the structure, including on the Minnesota ramps; replacing street lighting on the Wisconsin approach; applying a concrete sealer to the entire deck, including the Minnesota ramps; and placing new pavement markings on the entire bridge, Minnesota ramps and Wisconsin approach.
  • Traffic impacts: US 2 remains open to traffic, but:
  • On eastbound US 2, the inside lane and shoulder are closed from the north- and south I-35 ramps on the Minnesota side to the roundabout on the Wisconsin side.
  • On westbound US 2, the inside lane and shoulder are closed from the roundabout in Superior through the length of the project.
  • The following closures also are planned on the Minnesota side of the river:
    • Ramp from westbound US 2 to northbound I-35: Closed from 5 a.m. Monday, Oct. 27 to 7 p.m. Wednesday, Oct. 29.
      • Traffic is being detoured via the ramp from South 46th Avenue West to southbound I-35 to Central Avenue to northbound I-35.
    • South 46th Avenue West from WIS 35 to eastbound US 2: Closed from 5 a.m. Thursday, Oct. 30 to 7 p.m. Friday, Oct. 31 and 5 a.m. Monday, Nov. 3 to 7 p.m. Wednesday, Nov. 5.
      • Traffic will be detoured via southbound I-35, Central Avenue, northbound I-35 to eastbound US 2.
    • Southbound I-35 ramp to eastbound US 2: Closed 5 a.m. Monday, Nov. 10 to 7 p.m. Wednesday, Nov. 12.
      • Traffic will be detoured via southbound I-35 to Central Avenue to northbound I-35 to eastbound US 2.
    • Northbound I-35 ramp to eastbound US 2: Closed 5 a.m. Thursday, Nov. 13 to 7 p.m. Friday, Nov. 14.
      • Traffic will be detoured via northbound I-35 to South 27th Avenue West to southbound I-35 to US 2.
    • Sidewalk from Susquehanna Avenue in Superior across the bridge to West Michigan Street in Duluth will be closed from Monday to Monday, Nov. 3-24 because of work on the Bong Bridge rehabilitation project.
    • Closures are contractor and weather dependent.
US 53
  • Location: 2nd Avenue East to Hughitt Avenue in Superior
  • Schedule: July 14 to mid-September
  • Cost: $3.98 million
  • Description: For the road rehabilitation project: Milling 1.5 inches off the roadway between Hughitt Avenue and the bridge over the railroad tracks and overlaying the driving lanes with a 1.5-inch layer of asphalt; milling the existing asphalt pavement down to the concrete pavement between the bridge over the railroad tracks and 2nd Avenue East, making spot repairs to the underlying concrete and then placing 3 inches of new asphalt pavement; making spot curb and gutter repairs; repairing various inlets and storm and sanitary sewer manholes; upgrading or installing curb ramps at pedestrian crossings. For the safety project: Closing the existing median on US 53 at E Street; adding new turn bays on US 53 to for motorists turning right onto E Street; widening Lenroot Drive, currently a one-way street, to accommodate two-lane, two-way traffic; making improvements at the intersection of Lenroot Drive and Winter Street; and milling the existing pavement on Lenroot Drive, Winter Street and East 1st Street and then overlaying the roads with asphalt.
  • Traffic impacts: US 53 remains open to traffic, but motorists will encounter lane closures and a 10-foot width restriction.

Eau Claire County

US 12
  • Location: Industrial Drive in Altoona to the Fall Creek Bridge
  • Schedule: August 11 to early November
  • Cost: $4.48 million
  • Description: Milling and resurfacing the existing pavement with new asphalt; widening paved shoulders from 3 feet to 5 feet; installing shoulder and centerline rumble strips to enhance driver safety; repairing or replacing aging culverts and cattle passes; upgrading guardrail throughout the project; improving drainage by grading ditches south of US 12 near Schultz Road and west of Oak Knoll Road; installing new pavement markings throughout the corridor; and clearing trees from a 500-foot segment between Voight and Oak Knoll roads.
  • Traffic impacts: Motorists might encounter slow-moving construction vehicles during pavement marking and possible shoulder closures.
I-94
  • Location: US 53 interchange to Mallard Road southwest of Eau Claire
  • Schedule: March 17 and mid-November, 2025 construction; and March 4, 2024 to November 2026, overall project
  • Cost: $69.9 million
  • Description of 2025 work: Replacing the pavement of westbound I-94 from Otter Creek to Mallard Road, the westbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under westbound I-94 near County D.
  • Traffic impacts: I-94 is open to traffic, but:
    • Motorists will encounter single-lane closures during nonpeak travel hours and a 60-mph speed limit in both directions.
    • The speed limit in both directions is 60 mph.
    • County D is closed at I-94.

Jackson County

WIS 54
  • Location: Wilson and Mill Creek bridges west of Melrose
  • Schedule: June 23 to late November
  • Cost: $2.79 million
  • Description: Removing and replacing both bridges and replacing the pavement on both sides of each structure, guardrail and pavement markings.
  • Traffic impacts: WIS 54 is:
    • Closed at Wilson Creek; traffic is being detoured via US 53/WIS 93, I-90, WIS 16, WIS 108 and WIS 71.
    • Open at Mill Creek to a single lane of traffic controlled by temporary traffic signals.

Pepin County

WIS 35
  • Location: Walnut Street in Stockholm to the Pierce County line
  • Schedule: August 25 to early November
  • Cost: $4.28 million
  • Description: Removing 2.25 inches of existing pavement, paving 3.75 inches of new asphalt pavement, completing culvert work, replacing guardrail and placing new pavement markings.
  • Traffic impacts: Motorists will encounter daytime lane closures controlled by flagging and possible shoulder closures.

Pierce County

1005th Street
  • Location: Wind River Bridge in the town of Diamond Bluff southeast of Prescott
  • Schedule: September 16 to mid-November
  • Cost: $540,271
  • Description: Replacing the bridge, realigning the stream, placing riprap and completing approach work, including asphalt paving.
  • Traffic Impacts: The road is closed on each end at WIS 35.
County U
  • Location: County CC to 145th Avenue south of Plum City
  • Schedule: September 8 to early November
  • Cost: $1.49 million
  • Description: Pulverizing and relaying the existing pavement, placing new asphalt pavement, adjusting guardrail and placing new pavement markings.
  • Traffic Impacts: Motorists will encounter lane closures controlled by flagging.

Polk County

3rd Avenue
  • Location: Ash Street to Oak Street in Frederic
  • Schedule: September 23 to mid-November
  • Cost: $584,100
  • Description: Reconstructing the road, making storm sewer upgrades, completing curb, gutter and sidewalk work and replacing pavement markings and signage.
  • Traffic Impacts: The road is closed to through traffic.

St. Croix County

WIS 35
  • Location: South of I-94 between Stageline Road and Hanley Road/High Ridge Drive in Hudson
  • Schedule: August 20 to mid-September
  • Cost: $3.57 million
  • Description: Extending an existing noise wall on the west side of WIS 35 south of the existing noise wall between the highway and Heritage Boulevard and adding two noise walls on the east side of WIS 35 - one southwest of Meadows Park and northwest of the Canary Way cul-de-sac and the other between the highway and Meadowlark Drive and Meadowlark Lane.
  • Traffic impacts: Motorists will encounter the following impacts:
    • The right lane and shoulder are closed on northbound WIS 35 from the on-ramp from the Hanley Road/High Ridge Drive overpass to the exit direction until 6 tonight.
    • The exit lane on southbound WIS 35 will be closed from near the Stageline Road overpass to the Hanley Road/High Ridge Drive off-ramp until 6 tonight and from 7 a.m. Monday, October 27 until 6 p.m. Friday, October 31.
      • Vehicles can exit at Hanley Road/High Ridge Drive, but the exit point to the off-ramp is shifted south.
    • The auxiliary turn lanes from High Ridge Drive to the ramp to northbound WIS 35 and the ramp from southbound WIS 35 to Hanley Road are closed.
I-94
  • Location: Bridges over Kinney Road and 100th Street between Roberts and Hudson
  • Schedule: March 17 to mid-October, 2025 construction; and September 9, 2024 to mid-October 2026, overall project
  • Cost: $20.08 million
  • Description of 2025 work: Removing and replacing the westbound bridges and 1,000 to 1,200 feet of the I-94 pavement on both sides of structures in both directions; installing storm sewer; and replacing guardrail and pavement markings.
  • Traffic impacts: Motorists will encounter lane closures on eastbound I-94 the week of October 27 to patch the deck of the bridge over Kinney Road.

Sawyer County

County CC
  • Location: Bridge over the Chippewa Flowage southwest of New Post
  • Schedule: September 8 to early November
  • Cost: $613,953
  • Description: Replacing the bridge deck, making abutment repairs, replacing approach pavement, placing riprap and replacing guardrail.
  • Traffic Impacts: The road is closed at the bridge.

Taylor County

Elm Avenue and Robin Drive
  • Location: Deer Creek culverts on Elm Avenue and Robin Drive and West Branch Big Eau Pleine River Bridge on Elm, all southeast of Stetsonville
  • Schedule: May 27 to mid-November
  • Cost: $1.75 million
  • Description: At Deer Creek culverts on Elm Avenue and Robin Drive: Removing the culvert pipes, replacing them with bridges, reconstructing 50 feet of roadway on both sides of the new structures, completing grading and placing riprap between the abutments and stream edges. In addition, realigning the stream at Deer Creek on Robin Drive. At West Branch Big Eau Pleine River: Replacing the existing bridge and reconstructing 100 feet of approach roadway.
  • Traffic impacts: Elm Avenue is closed.
Grahl Drive
  • Location: East branch of Little Black River Bridge northeast of Medford
  • Schedule: September 22 to early November
  • Cost: $430,239
  • Description: Replacing the bridge and reconstructing 228.5 feet of approach pavement.
  • Traffic Impacts: The road is closed at the bridge.
County A
  • Location: Pine Creek Bridge southwest of Medford
  • Schedule: September 18 to late November
  • Cost: $658,724
  • Description: Replacing the bridge and approaching pavement.
  • Traffic Impacts: The road is closed between Oak and Wren drives.

Trempealeau County

US 10
  • Location: Nelson Road to I-94 westbound ramps in Osseo
  • Schedule: April 14 to late October
  • Cost: $5.78 million
  • Description: Removing the pavement from east of the Buffalo River State Park Trail to just west of Rose Lane and placing 8.5 inches of concrete pavement along with six inches of underlying base aggregate; repairing or replacing existing concrete pavement near I-94 at spot locations; making repairs to the US bridge over I-94; making concrete surface repairs on the bridge over the north fork of the Buffalo River and overlaying the deck with concrete; replacing storm sewer, sanitary sewer and water main; and replacing sidewalk, curb ramps, curb and gutter and pavement markings.
  • Traffic impacts: US 10 is open to traffic, but:
    • Motorists will encounter lane closures on the US 10 bridge over I-94 and shoulder and intermittent lane closures on westbound I-94.

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region: