WisDOT holding public involvement meeting on US 2 project

Proposed work in Ashland includes replacing pavement, storm sewer, traffic signals

Release date: November 5, 2026

The Wisconsin Department of Transportation (WisDOT) is holding a public involvement meeting to share details about a proposed pavement improvement project on US 2 from Stuntz Avenue to 36th Avenue East in the Ashland County city of Ashland and gather public input.

  • When: 4 to 7 p.m. Thursday, Nov. 19
    • A brief presentation is planned at 5 p.m. The rest of the meeting will follow an open-house format.
  • Where: Ashland City Hall, council chamber, 601 Main St. W.

The pavement on this segment of US 2 is showing signs of deterioration. To address this and other issues, WisDOT is proposing:

From Stuntz Avenue to 29th Avenue East: 

  • Replacing the existing pavement, base, subbase, curb and gutter 
  • Replacing traffic signals at 26th Avenue East
  • Replacing storm sewer, guardrail and pavement markings
  • Upgrading existing curb ramps to meet current American With Disabilities Act (ADA) standards
  • Replacing portions of the lighting and existing sidewalk
  • Investigating access modifications, turn-lane configurations and typical roadway sections along the route
    • The city sanitary also plans to make sanitary sewer and water main improvements.

From 29th Avenue East to 36th Avenue East include:

  • Performing concrete joint repair

Construction will be completed in stages with segments being partially closed with one westbound lane open to traffic and eastbound traffic detoured on local streets. Access to businesses and residences in the work zone will be accommodated. In addition, temporary pedestrian accommodations will be provided during sidewalk and curb ramp work.

Those unable to attend the public involvement meeting are invited to go to the project website, review information about the proposed work and submit comments by Dec. 19, 2026, by: 

  • Email: matthew.dickenson@dot.wi.gov
  • Mail: Wisconsin Department of Transportation, 1701 N. 4th St., Superior, Wi 54880 Attn.: Matt Dickenson

Construction currently is scheduled for 2031.

Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.

For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region:

For more information, contact:

Christena T. O'Brien, Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471, christena.obrien@dot.wi.gov


​

Back to top button