Release date: November 26, 2025
The Wisconsin Department of Transportation (WisDOT) provides weekly updates on road construction projects in the following counties in northwest Wisconsin: Ashland, Barron, Bayfield, Buffalo, Burnett, Chippewa, Clark, Douglas, Dunn, Eau Claire, Jackson, Pepin, Pierce, Polk, Rusk, St. Croix, Sawyer, Taylor, Trempealeau and Washburn counties.
Barron County
US 53 South
- Location: Bridges over US 8, 20th Street, Knapp Street, County I, Chetek River, County A, County AA and Carlson School Road between Cameron and New Auburn
- Schedule: May 5 to mid-December, 2025 construction; March 1 to late September, total project completion.
- Cost: $10.91 million
- Description of 2025 work: Replacing the decks on the bridges over County AA and County A; overlaying the decks with concrete on structures over Carlson School Road, Knapp Street and US 8; making miscellaneous repairs to bridges; completing prep work for 2026 construction on the bridges over the Chetek River, County I and 20th Street; and replacing guardrail at the structures.
- Traffic impacts: None, but motorists will encounter intermittent single-lane closures on County A and County AA and continuous single-lane closures on County I from December 1-12.
Chippewa and Eau Claire counties
US 53
- Location: Golf Road in Eau Claire to 40th Avenue in Lake Hallie
- Schedule for 2025: June 2 to early December. Bridge approach work at Otter Creek near US 12 (Clairemont Avenue) has been pushed to spring 2026.
- Cost: $10 million
- Description: Making repairs to or removing and replacing segments of concrete pavement; overlaying southbound US 53 with asphalt from WIS 312 (North Crossing) in Eau Claire to County OO in Lake Hallie; completing work at various structures; replacing guardrail; and placing new pavement markings.
- Traffic impacts: None, but traffic might be impacted the week of December 1 if traffic control items remain in the project limits.
Clark County
WIS 29
- Location: Koser Avenue west of Thorp to County D in Owen
- Schedule: May 1 to early December
- Cost: $23.74 million
- Description: Making repairs to the concrete pavement; placing 3.75 inches of new asphalt pavement over WIS 29; removing 1.25 inches of the existing pavement on the ramps at the WIS 29 interchanges at WIS 73 North/County M and WIS 73 South/County T and placing 2.25 inches of new asphalt; replacing the expansion joints on the east- and westbound WIS 29 bridges over the Black River west of Withee; replacing all wing walls on a culvert carrying the Popple River under WIS 29 west of County D in Owen; replacing the northwest wing wall on a culvert between Thorp and Withee; cleaning culverts and ditches; and replacing guardrail and pavement markings.
- Traffic impacts: None, but motorists are expected to encounter lane closures as finishing work resumes Monday, December 1.
Douglas County
US 2
- Location: Bong Bridge connecting Superior and Duluth, MN
- Schedule: August 6 to early December
- Cost: $6.38 million
- Description: Painting spot locations of the existing steel arch structure of the center span; making concrete surface repairs at spot locations of the two piers that support the center steel arch structure; removing and replacing three rubber strip seals of the center tied arch; replacing street lighting on the Minnesota half of the structure, including on the Minnesota ramps; replacing street lighting on the Wisconsin approach; applying a concrete sealer to the entire deck, including the Minnesota ramps; and placing new pavement markings on the entire bridge, Minnesota ramps and Wisconsin approach.
- Traffic impacts: None. In addition, the sidewalk from Susquehanna Avenue in Superior across the bridge to West Michigan Street in Duluth has reopened.
- Motorists will encounter traffic impacts as Wisconsin and Minnesota streetlight poles are installed. That work currently is anticipated to begin in mid-December on the Wisconsin side and in mid-January on the Minnesota side.
Eau Claire County
I-94
- Location: US 53 interchange to Mallard Road southwest of Eau Claire
- Schedule: March 17 and mid-November, 2025 construction; and March 4, 2024 to November 2026, overall project
- Cost: $69.9 million
- Description of 2025 work: Replacing the pavement of westbound I-94 from Otter Creek to Mallard Road, the westbound bridges over County J and County D and the box culvert carrying Kluckman Valley Creek under westbound I-94 near County D.
- Traffic impacts: None; construction is complete for 2025, and work will resume in 2026.
Jackson County
WIS 54
- Location: Wilson and Mill Creek bridges west of Melrose
- Schedule: June 23 to late November
- Cost: $2.79 million
- Description: Removing and replacing both bridges and replacing the pavement on both sides of each structure, guardrail and pavement markings.
- Traffic impacts: None; project complete.
Taylor County
Grahl Drive
- Location: East branch of Little Black River Bridge northeast of Medford
- Schedule: September 22 to early November
- Cost: $430,239
- Description: Replacing the bridge and reconstructing 228.5 feet of approach pavement.
- Traffic Impacts: The road is closed at the bridge.
Trempealeau County
US 10
- Location: Nelson Road to I-94 westbound ramps in Osseo
- Schedule: April 14 to early December
- Cost: $5.78 million
- Description: Removing the pavement from east of the Buffalo River State Park Trail to just west of Rose Lane and placing 8.5 inches of concrete pavement along with six inches of underlying base aggregate; repairing or replacing existing concrete pavement near I-94 at spot locations; making repairs to the US bridge over I-94; making concrete surface repairs on the bridge over the north fork of the Buffalo River and overlaying the deck with concrete; replacing storm sewer, sanitary sewer and water main; and replacing sidewalk, curb ramps, curb and gutter and pavement markings.
- Traffic impacts: None, but motorists might encounter a shoulder closure on westbound I-94 in December as work is completed..
Motorists are reminded that using handheld cell phones in Wisconsin work zones is illegal. Alerts and updates provided via these sites are not intended for use while driving. When driving, your focus should always be on driving.
For more information regarding traffic impacts, transportation news and improvement project updates in Wisconsin’s Northwest Region: