Release date: Friday, Oct. 16, 2026
The Wisconsin Department of Transportation (WisDOT) North Central Region provides interstate and state highway construction updates for the following counties in north central Wisconsin: Adams, Green Lake, Florence, Forest, Iron, Langlade, Lincoln, Marathon, Marquette, Menominee, Oneida, Portage, Price, Shawano, Vilas, Waupaca, Waushara and Wood counties.
Construction schedules may fluctuate pending weather conditions and crew availability.
Forest County
Highway: WIS 32
Location: US 8 to Crandon Railroad Overhead
Schedule: June 15 to October 2026
Project description: Crews will replace asphalt pavement, install new storm sewer and stormwater pond, replace sidewalk, and curb and gutter and install new pavement markings.
Anticipated work scheduled: Crews will:
- Pave the road
- Begin restoration
- Install guardrail
Traffic impacts:
- WIS 32 will be closed to thru traffic and detoured via US 8, US 45 and WIS 32. Local traffic will be able to access homes and businesses.
- East Glen Street intersection is now open with temporary stop signs.
- East Glen Street is closed until the end of October.
Lincoln County
Highway: WIS 107
Location: Wilderness Drive to County S
Schedule: May 26 to Oct. 23, 2026
Project description: Crews will repave the asphalt and repair or replace culverts.
Anticipated work scheduled: Crews will:
- Continue paving side roads
- Place shoulder material
Traffic impacts:
- The road will be closed to thru traffic. Traffic will be detoured using WIS 64, US 51, and County S.
Highway: WIS 17
Location: WIS 64 to Big Hay Meadow Creek
Schedule: Aug. 31 to Nov. 6, 2026; April 5 to July 30, 2027
Project description: This project will include replace the asphalt surface, replacing concrete curb and gutter, installing centerline rumble strips, and place protective thermoplastic coating at snowmobile crossings.
Anticipated work scheduled: Crews will:
- Continue paving operations
Traffic impacts:
- WIS 17 will be closed to through traffic. WIS 17 traffic will be detoured along WIS 64, US 51 and US 8.
Marathon County
Highway: WIS 29
Location: WIS 97 to Purple Martin Lane
Schedule: April 6 to Nov. 13, 2026
Project description: Crews will replace existing guardrail, repair concrete pavement, replace concrete pavement in five areas and replace a culvert under westbound WIS 29.
Anticipated work scheduled: Crews will:
- Finish grading and shaping intersections and turn lanes
- Finish paving asphalt shoulders on WIS 29 westbound
- Begin paving asphalt sideroads and intersections
- Place shoulder material on WIS 29 westbound
- Pour the six cracked panels of concrete
- Begin grooving for WIS 29 westbound pavement markings
- Begin rout and seal on WIS 29 westbound
Traffic impacts:
- WIS 29 eastbound and westbound lane closures.
- County H interchange ramp closure until Oct. 30, 2026
- County H through lanes are now open
Highway: WIS 29, US 51
Location: Foxglove Road to Bridge Street
Schedule: April 9 to Oct. 31, 2026
Project description: The purpose of the project is to address ongoing deterioration of concrete pavements, curb and gutter, inlets and bridges while addressing curb ramps that do not meet Americans with Disabilities Act (ADA) standards.
Anticipated work scheduled: Crews will:
- Install pavement markings and
- Replace guardrail
- Replace concrete pavement
- Install high friction surface treatment on WIS 29
- Mill and pave the asphalt shoulders
Traffic impacts:
A single lane closure will be installed along various locations along US 51 northbound, US 51 southbound, WIS 29 eastbound and WIS 29 westbound for daytime hours with daily nighttime rolling closures or lane closures restricting traffic to a single lane. The center lane will be closed along US 51 between the WIS 29 interchanges. Motorists will need to be in the outside lane to allow themselves to use exit ramps while the inside lane will be for thru traffic only.
Local road closures are along the following roadways:
- County NN
- Sherman Street
- Stewart Avenue
- WIS 52 Parkway
The following service ramps are closed and anticipated to be open by Oct. 21:
- US 51 southbound to County NN off-ramp
- County NN on-ramp to US 51 southbound
The following service ramps are closed and anticipated to be open by Oct. 26:
- US 51 northbound to Sherman Street off-ramp
- Stewart Avenue on-ramp to WIS 29 westbound
- WIS 29 esatbound off-ramp to Stewart Avenue
Marquette County
Highway: I-39 southbound
Location: Fawn Court to Waushara County Line
Schedule: Aug. 24, 2026 to Aug. 17, 2027
Project description: Crews will resurface the highway, repair and replace culverts, replace guardrail, reconstruct portions of the pavement along County E/J at the I-39 interchange, replace pavement and curb ramps at Rest Area 81, install lighting enhancements at Rest Area 81, construct drainage improvements at Rest Area 82 and replace pavement markings. Construction on I-39 is scheduled be completed by mid-November 2026. Construction on County E/J and Rest Areas 81 and 82 is scheduled for Spring 2027, with completion anticipated by mid-August 2027. The schedule is dependent on favorable weather conditions and construction progress
Anticipated work scheduled: Crews will:
- Pave the asphalt
- Place final grading
- Install guardrail in southern portion
Traffic impacts:
- Single lane closures on both I-39 southbound and I-39 northbound between Fawn Court and the Waushara County line.
- The I-39 southbound exit ramp at County E/J in Westfield will be closed on Oct. 22. The short-term closures will be over the next two weeks and will only be closed when necessary. A detour route will be available for the motorists when the ramps are closed.
Menominee County
Highway: WIS 47
Location: WIS 55 to the Langlade County Line
Schedule: June 22 to Oct. 30, 2026
Project description: Crews will repave the road, replace small culverts, repair or replace guardrail, replace curb and gutter, and install new pavement markings.
Anticipated work scheduled: Crews will:
- Install erosion control
- Replace culvert
- Patching at culvert replacements
- Continue milling at WIS 47
Traffic impacts:
- WIS 55 is closed to thru traffic from WIS 47 to the Langlade County Line for patching and grading operations. Thru traffic will be detoured via WIS 22, WIS 32 and WIS 64. Access by local traffic and emergency services will be maintained throughout the closure. The closure is anticipated to continue until late October.
- WIS 47 will be reduced to a single lane by flagging for asphalt pavement milling operations
Oneida County
Highway: US 51
Location: Minocqua Bridge to Front Street
Schedule: April 6 to June 18, 2026 and Sept. 8 to Oct. 20, 2026
Project description: The project will include concrete joint repairs, curb and gutter improvements and reconstruction of curb ramps to meet ADA standards.
Anticipated work scheduled: Crews will:
- Pour concrete in repair areas
- Begin installing pavement markings
Traffic impacts:
- Northbound and southbound driving lane closures from Minocqua bridge to Front Street.
- 10-foot width restrictions will be posted in the work zone.
Shawano County
Highway: WIS 29
Location: County M to Highline Road
Schedule: April 13 to Oct. 20, 2026
Project description: The purpose of this project is to repair concrete joints, replace sections of deteriorated concrete pavement, mill and overlay the asphalt shoulders and replace the guardrail.
Anticipated work scheduled: Crews will:
- Install pavement markings
- Grind the concrete replacement
- Install guardrail
Traffic impacts:
- WIS 29 eastbound and westbound traffic will be on the inside lanes.
- County K on and off ramps for WIS 29 westbound will open next week Tuesday, Oct. 13.
- WIS 47/117 westbound on and off ramps for WIS 29 to close Wednesday, Oct. 14 thru Saturday Oct. 17 for concrete diamond grinding.
Highway: WIS 29
Location: County J to County M, Eastbound
Schedule: March 30 to Nov. 20, 2026
Project description: Crews will replace existing guardrail, repair concrete pavement, replace concrete pavement in five areas and replace a culvert under westbound WIS 29.
Anticipated work scheduled: Crews will:
- Install pavement markings and rumble strips
- Continue concrete replacement in the inside lanes
Traffic impacts:
- WIS 29 will have single lane closures
Waupaca County
Highway: US 45
Location: County C to Gollnow Road
Schedule: April 20 to Oct. 30, 2026
Project description: The work will consist of removing and replacing asphalt pavement northbound and southbound on US 45. The project will also consist of re-grading the existing ditch south of Gollnow Road, replacing deteriorated curb and gutter at intersection and median areas, replacing guardrail and replacing storm sewer inlets.
Anticipated work scheduled: Crews will:
- Continue paving the asphalt
Traffic impacts:
- Traffic is shifted to southbound US 45, with one lane per direction until October.
- Motorists will encounter flaggers near the intersections. Traffic may be directed to use the nearest connected intersection during paving operations.
Highway: US 10
Location: Anderson Road to Appletree Lane
Schedule: May 4 to Nov. 2, 2026
Project description: Work includes completing joint repairs and replacement, replacing the asphalt shoulders, replacing guardrail, inlet repairs as needed, new pavement marking and replacing curb ramps that are not compliant with Americans with Disabilities Act standards.
Anticipated work scheduled: Crews will:
- US 10 westbound
- Complete machine paving for large concrete pavement replacement locations on the inside lane (passing lane)
- Remove concrete for concrete pavement repair and replacement locations on the inside lane (passing lane)
- Pour concrete for concrete pavement repair and replacement locations on the inside lane (passing lane)
- WIS 22
- Complete concrete pavement repairs.
- WIS 49/54
- Complete removals for concrete pavement repair and replacement locations on the outside lane (driving lane)
- Pour concrete for concrete pavement repair and replacement locations on the outside lane (driving lane)
- Switch traffic to start removals of the inside lane (passing lane)
- Start removals for concrete pavement repair and replacement locations on the inside lane (passing lane)
Traffic impacts:
- US 10
- The westbound inside lane (passing lane) and shoulder will be closed from Vaughan Road to Anderson Road.
- The eastbound outside lane (driving lane) and shoulder will be closed from Anderson Road to WIS 54.
- WIS 22 South / Lakeside Parkway
- The southbound inside lane is closed from ¼ mile north to ¼ mile south of US 10.
- Starting Oct. 19, the eastbound US 10 off-ramp to WIS 22 will be right turn only onto WIS 22.
- WIS 49/54
- The eastbound and westbound outside lane and shoulder will be closed from west of County QQ to Covered Bridge Road.
- Starting Oct. 23, the eastbound and westbound inside lane and shoulder will be closed from west of County QQ to Covered Bridge Road.
Highway: US 10 westbound
Location: Old WIS 49 to Winnebago County Line
Schedule: Aug. 10 to Nov. 12, 2026
Project description: Crews will be replacing concrete in the travel lanes, repaving the asphalt shoulders, replacing guardrail, and re-striping US 10; updating the signals at the WIS 96 / WIS 110 intersection; and replacing concrete in the travel lanes, and repaving the asphalt shoulders along WIS 110 from the ramp terminals to the WIS 96 intersection.
Anticipated work scheduled: Crews will:
- Start traffic signal work at the intersection of WIS 96 and WIS 110
- Continue concrete pavement repairs and replacements on westbound US 10 for the outside lane (driving lane)
Traffic impacts:
- The westbound outside lane (driving lane) and shoulder of US 10 is closed from Marsh Road to Old WIS 49.
- The westbound US 10 off-ramp to WIS 96/110 is closed. Motorist should follow the posted detour.
- The westbound US 10 on-ramp from WIS 96/110 is closed. Motorist should follow the posted detour.
- The northbound and southbound outside lanes and shoulders of WIS 96/110 is closed.
Wood/Portage County
Highway: WIS 13/34
Location: 2nd Street North to County P
Schedule: April 13 to November 2026
Project description: This project will include replacing the asphalt, culvert replacements, bridge rehabilitation and guard rail replacement.
Anticipated work scheduled: Crews will:
- Install shoulder gravel.
- Place polymer overlay on structure.
- Install pavement marking
- Install centerline rumble strip
Traffic impacts:
- WIS 13 will be closed to thru traffic from 2nd Street North to County P. Traffic will be detoured via WIS 66, I-39, and US 10.
- Access within the project will be down to one lane during milling operations. Property owners should expect short-term blocking of their driveways during the milling and relay operations.
Highway: WIS 54
Location: 26th Street North to County B
Schedule: April 14 to Oct. 31, 2026
Project description: Crews will replace concrete joints, curb and gutter, and upgrade pedestrian curb ramps.
Anticipated work scheduled: Crews will:
- Continue removals and concrete work for the pavement repairs along the outside lane in the westbound direction. Crews will begin working on the pavement repairs and curb ramps in and around the WIS 54/County B/Post Road intersection.
- Continue to work on the inlet adjustments in Plover and Wisconsin Rapids.
- Grind the concrete pavement repairs on WIS 54 in the urban areas in the eastbound outside lane.
- Finish sweeping the milled surface at the outside shoulders and intersection approaches.
- Pave asphalt pavement for the outside shoulders and intersection approaches.
- Prepare the topsoil around the curb ramps and inlet adjustments, place seed and fertilizer, and cover those areas with erosion mat.
- Work on the traffic loop replacements at the WIS 54/County B/Post Road intersection.
- Saw the pavement and curb and gutter for removals in the WIS 54/County B/Post Road intersection.
Traffic impacts:
- The outside lane in the eastbound and westbound directions WIS 54 will be closed to traffic from 26th Street North in Wisconsin Rapids to Bus 51/Post Road in Plover.
- Motorists can expect right turn lane closures at the WIS 54/County B/Post Road intersection
Wood County
Highway: WIS 73
Location: County U and WIS 13
Schedule: Sept. 21 to Oct. 30, 2026
Project description: Crews will be resurfacing the highway, replacing guardrail and curb and gutter at the bridge, and adding end walls to a culvert.
Anticipated work scheduled: Crews will:
Traffic impacts:
- Single-lane closures with flaggers