Location
US 45, WIS 32 to Vilas County Line, Oneida County
Overview
The proposed improvements include milling off the top two inches of the roadway surface and paving two new inches of asphaltic pavement. The curb ramps will be reconstructed to meet current Americans with Disabilities Act (ADA) standards to the maximum extent practical. Seven culverts will be replaced.
Traffic Impacts
During construction, US 45 will remain open to through traffic, but may be limited to one lane during daytime with the use of flaggers. Staged sidewalk closures will also be necessary during curb ramp construction.
Schedule
Local officials meeting: September 2019
Public involvement meeting: May 2020
Complete project design: February 2022
Construction currently scheduled to begin: Summer 2022