Overview

This proposed project will rehabilitate the existing culvert carrying WIS 107 over Joe Snow Creek, replace the existing culvert carrying WIS 107 over Skanawan Creek and replace the two culverts south of County J.

Traffic Impacts

Each of these projects will be constructed under a full detour with efforts made to minimize the impact to local residents and businesses.

Schedule

  • Local Officials Meeting: June 9, 2020
  • Public Involvement: August, 2020
  • Complete Project Design: May 2022
  • Construction currently scheduled to begin: Summer 2023

Pine Creek Bridge Update

Update: January 25, 2021

A 40-ton load posting was placed on WIS 107 in October 2020 due to the deterioration of the 2 large steel culverts at Little Pine Creek, 2.3 miles south of County S near Tomahawk. Signs were installed to notify the traveling public. Due to their condition, their replacement has been moved up to 2022.

  • Complete Project Design for Pine Creek Bridge: November 2021
  • Little Pine Creek Construction: Summer 2022

​Contacts

WisDOT Project Manager: Stacy Hagenbucher, (715) 365-5770

Wisconsin Department of Transportation (WisDOT)
North Central Region, Wisconsin Rapids Office
510 Hanson Lake Road
Rhinelander, WI 54501
Phone: (715) 365-3490
Fax: (715) 365-5780
TTY: 711