WIS 13 (Little Black River Bridge), town of Little Black - Taylor County

Location

Little Black River Bridge south of Medford in Taylor County.

Overview

The bridge deck is showing signs of deterioration. To address this, the Wisconsin Department of Transportation is proposing to:

  • Replace the bridge deck.
  • Add concrete approach slabs.
  • Complete approach work.
  • Upgrade guardrail.
  • Add pavement marking.

Schedule

  • Construction currently is scheduled for 2026.

Traffic Impacts

WIS 13 will be closed and detoured during construction.

  • Access to properties in the work zone will be maintained during construction.

Contacts

Adam Hetrick
WisDOT Northwest Region Project Manager
(715) 577-8053
adam.hetrick@dot.wi.gov

David Koepp
WisDOT Northwest Region Project Supervisor
(715) 836-2399
david.koepp@dot.wi.gov

Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 828-9471
christena.obrien@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire, WI 54701
(715) 836-2891, (800) 991-5285
nwr.dtsd@dot.wi.gov