Completed WIS 125/College Avenue design-build project

WisDOT's first design-build pilot project is open to traffic and nearing completion. The structure on WIS 125/College Avenue in the town of Grand Chute, Outagamie County, reopened to traffic Oct. 31, 2023, within budget and on a compressed schedule.

  • Cost: $3.8 million
  • Two months to complete
  • Structure replacement on WIS 125 over Mud Creek just east of I-41
  • Replacement of box culvert and work on pavement, curb and gutter, storm sewer and beam guard

WisDOT is looking closely at how design-build contracts can minimize construction impacts while delivering quality work. That learning process is ongoing as the department continues to evaluate design-build as an alternative contracting method. Congratulations to the project team

WIS 125 6526-00-71 - Project Description

  • I-41 – Bluemound Dr., Outagamie County, Northeast Region
  • Removal of a multi-cell box culvert and replacement with a slab span structure on College Avenue in Appleton
  • WIS 125 Best Value Score Results
    • Proposals received: August 19, 2022
    • Results posted: September 9, 2022
    • The Highest Adjusted Score is the Best Value Proposal and the project will be awarded to the associated design-builder.
    Design-
    Builder
    Technical Proposal ScoreCost Proposal Amount Amount Exceeding Lowest Proposal Percent Exceeding Lowest Cost Proposal Price ScoreAdjusted Score
    Pheifer Bros30.51$3,806,945.86-N/A6090.61
    KNA31.8$5,247,705.00$1,440,759.1437.85%37.2968.47
  • Schedule
    • May 27, 2022 - Clarification Submittal #1 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
    • June 2, 2022 - One-on-One Meeting on RFP and Initial ATCs
    • June 7, 2022 - DBE Meet and Greet
    • June 17, 2022 - Clarification Submittal #2 and One-on-One Meeting Agenda Deadline (5:00 pm Central Time)
    • June 23, 2022 - One-on-One Meeting on RFP and Initial/Final ATCs
    • July 1, 2022 - Initial ATC Submittal Deadline (5:00 pm Central Time)
    • July 8, 2022 - Department ATC Response Date
    • July 29, 2022 - ATC Resubmittal Deadline (5:00 pm Central Time)
    • August 1, 2022 - Final Clarification Deadline (5:00 pm Central Time)​
    • August 1, 2022 - SOQ Modification Request Deadline (5:00 pm Central Time)
    • August 5, 2022 - Department ATC Final Response Date
    • August 10, 2022 - Department SOQ Modification Request Response Date
    • August 10, 2022 - Department Clarification Response Date
    • August 19, 2022 - Proposal (Technical Proposal and Price Proposal) Due Date (3:00 pm Central Time)