I-41 Improvements - Fond du Lac County

Northern Fond du Lac and southern Winnebago County: Resurfacing and Culvert Replacement (Project ID 1100-52-00)

  • Project ID 1100-52-00: Resurfacing and culvert replacement: I-41 between County D in Fond du Lac County and WIS 26 in Winnebago County.​
  • View project location in pdf

Project need

WisDOT is proposing to improve 14.2 miles of I-41. The existing pavement and cable guard system are both beginning to deteriorate and will require increased maintenance. Both will reach the end of their service life by the time of construction. The guardrail will also be replaced to meet current safety standards. Also, drainage measures are needed to prevent water overtopping I-41 north of County Z to Black Wolf Avenue in the town of Nekimi, southern Winnebago County. A box culvert replacement will improve drainage.

Proposed improvements

  • Mill and overlay two (2) inches of asphalt along the Northbound and Southbound lanes
  • Replace cable barrier and guardrail along I-41 mainline and ramps
  • Miscellaneous structure maintenance work
  • Miscellaneous culvert extension and slope flattening work
  • Replace existing box culvert to address flooding issue North of County Z
  • View project construction display

Proposed schedule

  • Environmental document: February 2022
  • Design study: March 2022
  • Utility coordination: April 2022
  • Design completion: August 203
  • Construction is currently scheduled in 2026
  • Construction may be advanced to 2024 should funding become available
  • Please see website for schedule updates

Traffic Impacts

I-41: The interstate will remain open to traffic during construction with the following restrictions:

  • Mainline paving, cable barrier, guardrail, and I-41 structure maintenance
    • Night work or off-peak hours
    • Maintain one lane in each direction
  • Box culvert construction north of County Z
    • Construct temporary crossovers
    • Maintain 2 lanes in each direction during peak hours

Side roads: Overpass and structure work affecting off-interstate traffic

  • County D, WIS 23, County OO, WIS 26
    • Work will be conducted using lane closures and/or flagging operations
  • County OOO, County OO (Scott Street), County Z, Lincoln Road
    • Full closures are anticipated.

New right-of-way or temporary limited easements may be required at select culvert replacement locations.

Public input/comments

Your comments are important to us to obtain input that will assist the department in the further development and refinement of a final design. Please feel free to download, print, and share with anyone who does not have access to this website.

Attached to the handout is a comment form for written comments with a prepaid mailer. Please mail any written comments or e-mail comments to one of the contacts listed below.

Business planning resources

WisDOT recognizes businesses and organizations located in work zones have special needs. WisDOT's "In This Together" program is designed specifically for business and community leaders as an idea source as they plan for road construction. The In This Together program includes:

  • An interactive Business Communication Guide with tips, tools, and resources
  • Case studies that demonstrate techniques in other communities
  • Promotional samples to promote your business during construction
  • View WisDOT's In This Together website

Project contacts

Ryan Erdmann, P.E.
Project Manager
WisDOT Northeast Region
944 Vanderperren Way
Green Bay, WI 54304-5344
Phone: (920) 370-2642
ryand.erdmann@dot.wi.gov

Rob Wagner, P.E.
Project Supervisor
WisDOT – Northeast Region
944 Vanderperren Way
Green Bay, WI 54304-5344
Phone: (920) 445-9925
robert.wagner@dot.wi.gov