WIS 47 and County S Intersection Improvements

NEW IN 2025: Single lane roundabout selected. project map

The Wisconsin Department of Transportation (WisDOT) is in the process of developing plans for proposed improvements at the intersection of WIS 47 and County Road S in the town of Center in Outagamie County. This website details proposed improvements, describes the potential impacts it would have on the community, and offers an opportunity for public comment.

Location

WIS 47 and County Road S intersection is located between Appleton and Black Creek in the town of Center, Outagamie County.

Project purpose and need

The purpose of the proposed action is to improve the safety at the intersection of WIS 47 and County Road S while providing acceptable traffic operations. The need for the proposed improvement is to reduce the number and severity of crashes at the intersection, particularly right-angle type crashes, and to improve the traffic operations of the intersection.

  • The intersection of WIS 47 and County Road S had 16 crashes from 2017 to 2021, 11 of which caused injuries.
  • Of the sixteen crashes, twelve were right angle crashes.

Proposed improvements

roundabout mapThis is a reconstruction-level project. The selected alternative is a single lane roundabout.

  • Improved safety at the intersection by installing a single lane roundabout
  • New pavement structure
  • New pavement marking and signing
  • New culvert and/or storm sewer installation
  • Intersection lighting

Roundabout

This alternative includes reconstructing the WIS 47 and County Road S intersection as a single lane roundabout. The roundabout would decrease speeds through the intersection and eliminate right angle crashes within the intersection, which is predicted to reduce the number of severe crashes at the intersection. A roundabout intersection would have significantly less traffic delay when compared to the all-way stop alternative.

Traffic impacts

The WIS 47 and County Road S intersection will be closed during construction and detour routes would be posted. Local access to property owners and businesses within project limits will be maintained throughout the project.

Schedule

  • Virtual Public Involvement meeting: May 24, 2023
  • Finalize alternative selection in July 2023
  • Environmental Document Approval: October 2024
  • Real estate acquisition is anticipated to begin in spring 2025
  • Design is on-going and will continue through fall of 2026
  • Construction is tentatively scheduled for 2027

Real estate

Right-of-way acquisition in the form of Temporary Limited Easement (TLE) and permanent acquisition (FEE) for will be required to accommodate reconstruction of the intersection. A member of the real estate team will contact affected property owners at the start of the acquisition process.

Business Resource: WisDOT’s In This Together program

WisDOT recognizes businesses located in work zones or impacted by detour routes have special needs. WisDOT's In This Together program is offered to business, organizations and community leaders as an idea source as they plan for road construction in their area. It includes promotional examples, case studies and a specially designed Business Coordination Guide with information on:

  • Planning ahead
  • Staying informed
  • Keeping customers informed
  • Tips for businesses

Please visit the WisDOT’s In This Together website to learn more.