US 53 (Various bridges), towns of Oak Grove and Stanley and city of Rice Lake - Barron County

Location

This project in Barron County includes the following structures on or over US 53:

  • North- and southbound US 53 bridges over US 8 in the town of Stanley
  • Augusta Street Bridge over US 53 in the city of Rice Lake
  • Northbound US 53 bridge over County SS and the Wild Rivers State Trail in the town of Oak Grove

Overview

Built between 1972 and 1983, the bridges are experiencing deterioration of the paint on the steel girders and bearings, which can lead to rusting and early failure of the structural steel components. To address this, the Wisconsin Department of Transportation is proposing the following:

  • North- and southbound US 53 over US 8:
    • Cleaning and painting bridge girders and bearings
    • Replacing guardrail within the US 8 median
  • Augusta Street over US 53:
    • Cleaning and painting bridge girders and bearings
    • Replacing guardrail within the US 53 median
  • US 53 northbound over County SS and the Wild Rivers Trail
    • Cleaning and painting bridge girders
    • Replacing guardrail on the east side of County SS

Schedule

Construction currently is scheduled in 2028.

  • Construction is anticipated to take approximately three months.

Traffic Impacts

The following traffic impacts are anticipated at the structures:

  • North- and southbound US 53 over US 8:
    • US 53 will remain open to traffic with periodic single-lane closures.
    • US 8 will remain open to traffic with single-lane closures.
  • Augusta Street over US 53
    • US 53 will remain open to traffic with single-lane closures.
    • Augusta Street will be closed to accommodate contractor access.
  • US 53 northbound over County SS and the Wild Rivers State Trail
    • US 53 will remain open to traffic with periodic single-lane closures.
    • One lane of traffic controlled by temporary traffic signals will be maintained on County SS.
    • Traffic on the Wild Rivers State and Ice Age trails will be detoured on local roads from 25th Avenue to 19th Street to 26th Avenue.

Contacts

Andrew Peterson
WisDOT Northwest Region Consultant Project Manager
(608) 792-6851
apeterson@correinc.com

Matt Van Natta
WisDOT Northwest Region Project Supervisor
(715) 392-7966
matthew.vannatta@dot.wi.gov

Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior office
1701 N. 4th St.
Superior, WI 54880
(715) 392-7925, (800) 590-1868
nwr.dtsd@dot.wi.gov