Location
This project is north of the Dunn County city of Menomonie on WIS 25 at its intersections with County BB West (south junction) and County BB East (north junction).
Overview
Both intersections have a high number of crashes. To address this and lessen the severity of crashes at both intersections, the Wisconsin Department of Transportation is proposing:
- Building a four-leg, single-lane roundabout at the intersection of WIS 25, County BB East and Northline Road.
- Currently, traffic is free flowing on WIS 25, and there are stop signs on County BB West and Northline Road at WIS 25.
- There is also a stop sign controlling traffic heading south on County F, which intersects Northline Road just to the west of its intersection with WIS 25.
- The County F/Northline Road intersection would be relocated to the west of the current crossing
- Building a four-leg, single-lane roundabout at the intersection of WIS 25, County BB West and Walton Avenue
- Currently, traffic is free flowing on WIS 25, and there are stops signs on County BB West and Walton Road and WIS 25.
Real Estate
Real estate acquisition will be required to construct the roundabouts at both locations.
Schedule
Construction currently is scheduled for 2031, but work will be advanced if possible.
Traffic Impacts
During construction, WIS 25 is expected to remain open to traffic, but motorists will encounter lane closures controlled by flagging.
Contacts
Jennifer Leech
WisDOT Northwest Region Traffic Safety Engineer
(715) 836-2853
jennifer.leech@dot.wi.gov
Stacey Rusch
WisDOT Northwest Region Traffic Unit Supervisor
(715) 836-3919
stacey.rusch@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire, WI 54701
(715) 836-2891, (800) 991-5285
WI Telecommunications Relay System (TTY): 711
nwr.dtsd@dot.wi.gov