WIS 27 (Sandy Run Creek), town of Brule - Douglas County

Location

The project is on WIS 27 at the Sandy Run Creek crossing near the WIS 27/US 2 intersection in the Douglas County town of Brule.

Overview

The culvert carrying Sandy Run Creek under the highway is nearing the end of its service life. The Wisconsin Department of Transportation is proposing to:

  • Remove the existing culvert
  • Replace it with a single-span concrete girder bridge
  • Replace approach pavement and guardrail
  • Place new pavement markings

Schedule

Construction currently is scheduled for 2026.

Traffic Impacts

During construction, WIS 27 will be closed at the construction site, and through traffic will be detoured via County A and County N.

Contacts

Matt Dickenson
WisDOT Northwest Region Project Manager
(715) 395-3022, (715) 225-9446
matthew.dickenson@dot.wi.gov

Matt Van Natta
WisDOT Northwest Region Project Supervisor
(715) 392-7966
matthew.vannatta@dot.wi.gov

Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior Office
1701 N. 4th St.
Superior, WI 54880
(715) 392-7925, (800) 590-1868
WI Telecommunications Relay System (TTY): 711
nwr.dtsd@dot.wi.gov