County X bridge over WIS 29 in the Chippewa County village of Boyd.
Overview
Built in 1963, the bridge is in need of rehabilitation. The Wisconsin Department of Transportation is proposing to:
- Replace the bridge deck
- Paint girders and bearings
- Make concrete surface repairs to bridge columns and then fiber wrap them
- Add concrete approach slabs on either side of the structure
- Reconstruct the pavement approaching the bridge
- Replace guardrail and pavement markings.
Schedule
Construction currently is scheduled for 2028.
Traffic Impacts
During construction:
- County X will be closed, with traffic detoured via County D and County V.
- WIS 29 will remain open to traffic, but single-lane closures during non-peak travels times will be necessary to complete the work.
- Nightly closures of the on- and off-ramps at the County X/WIS 29 interchange might be required.
Contacts
Max Sebesta
WisDOT Northwest Region Consultant Project Manager
(608) 667-4377
maxwell.sebesta@wsp.com
Nick Pitsch
WisDOT Northwest Region Project Supervisor
(715) 392-7976, (715) 225-1271
nicholas.pitsch@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Eau Claire Office
718 W. Clairemont Ave.
Eau Claire, WI 54701
(715) 836-2891, (800) 991-5285
nwr.dtsd@dot.wi.gov