Project Overview:
The slope on the east side of WIS 57, just south of the Ozaukee/Sheboygan County line (County K), has had ongoing erosion since it was constructed in 2001. This project will make improvements to stabilize this slope.
Proposed Improvements:
A geotechnical exploration was conducted on the slope to identify the best solution. Proposed solution:
- Install vertical rigid elements (miniature pilings driven into the embankment to strengthen the slope)
Traffic Impacts:
Single lane and shoulder closures are anticipated for pavement and median work. This project will require short-term full closures of northbound WIS 57 to replace a culvert and access the top of the slope repair area. A detour will be posted during the northbound closures.
Schedule:
This project is scheduled to begin in 2026.
Status:
Design Phase - If you have any questions about that project, please feel free to contact the project representatives below.
Contact Information:
Martin Villaca
WisDOT Design Project Manager
(262) 548-6456
martin.villaca@dot.wi.gov
Chris Verhyen
WisDOT SE Region Communications
(262) 548-8757
chris.verhyen@dot.wi.gov