Project Overview

This project will make various improvements along approximately four (4) miles of I-94, between County Q and County Y, including the replacement of the bridge structures over the Rock River and Crawfish River in Jefferson County.

Proposed Improvements

This project will replace the four I-94 bridge structures over the Rock River and Crawfish River. The new bridges will be built with three lanes to accommodate the future potential widening of I-94.
This project will also raise the I-94 roadway to prevent any future potential flooding. The westbound roadway will be raised by 3 to 5 feet near the bridges and the eastbound roadway will be raised by 1 to 2 feet near the bridges.

Proposed Traffic Impacts

  • I-94 will remain open to at least one lane of traffic in both directions during construction.
  • Access to the rest area (Rest Area 14) along westbound I-94 will be closed during construction of the westbound lanes.
  • The project plans will also address traffic control measures for watercraft on the Rock and Crawfish Rivers during the bridge replacement work.

Real Estate

Additional right-of-way may be required.

Schedule

Construction is scheduled to begin in early 2027 and last until fall 2028.

Status

Design phase - if you have any comments or questions about this project, please contact the project representative listed below.

Contact Information

Alex Grasse, PE
WisDOT Project Manager
(414) 750-1404
alex.grasse@dot.wi.gov

Chris Verhyen
WisDOT SE Region Communications
(262) 548-8757
chris.verhyen@dot.wi.gov