Project location
County C bridge over I-90, West Salem - La Crosse County
Project overview
The bridge will receive a deck overlay, existing beam guard will be updated to Midwest Guardrail System (MGS) guardrail, and new drainage inlets will be installed. The bridge deck showed signs of delamination (roughly 25% of deck) from an infrared survey. The proposed project is required to address the issues and maintain connectivity along County C.
Schedule
- October 2023 - Public Involvement
- August 2024 - 2nd Public Involvement
- 2027 - Construction anticipated
Traffic impacts/detours
Traffic will be under temporary traffic signals.
Status/phase
Design
Contact information
Cory Mikshowsky, P.E.
WisDOT Project Manager
(608) 789-6335
cory.mikshowsky@dot.wi.gov
Hannah Punzel
WisDOT Southwest Region Communications Manager
(608) 246-7907
hannah.punzel@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Southwest Region, La Crosse Office
3550 Mormon Coulee Road
La Crosse, WI 54601
Phone: (608) 785-9022
TTY: 711
Email:
swr.dtsd@dot.wi.gov