Project location |
Project overview |
Schedule |
Traffic impacts/detours |
Status/phase |
Contact information
Project location
WIS 113 (Lodi city limits to WIS 60), Lodi - Columbia County
Project overview
The project is planned to replace 0.5 miles of deteriorated pavement on WIS 113 from the southern Lodi City limits to the WIS 60 intersection in Columbia County. The proposed improvements include the following:
- Milling and overlaying 4.5 inches of new asphaltic material between the City of Lodi southern limits and the County K intersection
- Removing all the existing pavement and pavement structure, installing 16 inches of new subbase materials, installing 12 inches of new base materials and paving 5.5 inches of new asphaltic material between the County K intersection and the bridge over Spring Creek
- Repairing and replacing the existing concrete pavement between the bridge over Spring Creek and the WIS 60 intersection
- Replacing 12 existing curb ramps to meet current Americans with Disabilities Act standards
Schedule
- Summer 2025 - Public Involvement Meeting #1
- Spring 2027 - Public Involvement Meeting #2
- 2030 - Construction anticipated
Traffic impacts/detours
WIS 113 will be closed to through traffic during construction utilizing a detour along WIS 60, I-39/90/94 and WIS 19.
WisDOT recognizes businesses located in work zones have special needs. Its critical that customers have access to businesses and that they continue to visit them, regardless of any road work inconvenience and detour route. Below are resources to help business owners prepare for construction
Status/phase
Design
Contact information
Mahesh Shrestha, P.E.
WisDOT Project Manager
(608) 245-2674
mahesh.shrestha@dot.wi.gov
Hannah Punzel
WisDOT Southwest Region Communications Manager
(608) 246-7907
hannah.punzel@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
TTY: 711
Email: swr.dtsd@dot.wi.gov