I-94 Crawfish and Rock River Bridge Replacements, Jefferson County

Design Build-Program | Information for Industry | Design-Build Projects | Sign up for Updates

Project includes four structures and road work between the structures.

Anticipated release date January 29, 2026.


Anticipated Schedule
  • Request for Qualification (RFQ) released
  • Statement of Qualification (SOQ) due date - January 7, 2026
  • Announcement of Short-listed Proposers and Request for Proposers (RFP) release - January 29, 2026
  • Technical Proposal Due - May 19, 2026
  • Cost Proposal Due - June 9, 2026
  • Notification of Apparent Successful Proposer - June 17, 2026
  • Potential early construction in late 2026 with main construction in 2027 and 2028 construction seasons