Oregon/Jackson Street Bridge Study - Schedule

This page outlines the proposed schedule for the Oregon/Jackson Street Bridge Study and any potential improvement project construction. All schedules are subject to change.

Current (this year)

  • WisDOT received approval on our environmental document in February 2024 that includes a high-level fixed bridge on a partially offset alignment, as our preferred alternative.

Future (next year and beyond)

  • 2025-27: Final design phase
  • 2025-27: Real estate acquisition
  • 2027-28: Utility relocations
  • 2028: Construction begins on selected alternative
  • 2029/30: Construction complete

Past (anything prior to today)

  • February 2024 - Environmental document approved
  • June 2022 - Oshkosh City Council votes 7-0 in favor of high level fixed bridge
  • March 2022 - Oshkosh City Council workshop
  • April 2022 - PIM #3 for environmental study
  • Summer 2021 - WisDOT resumes environmental study
  • Late 2017 - WisDOT suspends environmental study
  • May 2017 - Oshkosh City Council votes 4-3 in favor of Alternative F
  • January 2017 - Oshkosh City Council workshop
  • October 13, 2016 – Public involvement meeting (PIM) #2 for environmental study
  • 2016/2017 – Study discussion and coordination with city of Oshkosh officials
  • April 27, 2016 – PIM #1 for environmental study
  • Fall 2015 – Environmental study began