US 151 (CNW Railroad to WIS 33), Beaver Dam - Dodge County

Project overview

US 151 between 0.5 miles south of CNW Railroad to 0.4 miles north of WIS 33 are experiencing pavement cracking, spalling at the joints and deterioration of shoulders. Additional Improvements include:

  • Concrete pavement patching
  • Asphalt shoulder replacement
  • Guardrail replacement
  • Miscellaneous culvert repairs or linings

Various structure work includes:

  • Surface repairs
  • Approach slab replacements
  • Slope paving repairs
  • Deck repairs
  • Deck sealing
  • Spot painting

Schedule

  • 2028 - Construction anticipated but could advance to 2027 if funding becomes available.

Traffic impacts/detours

Updates will be provided as design progresses.

Status/phase

Design

Contact information

Craig Hardy, P.E.
WisDOT Project Manager
(608) 246-5406
craig.hardy@dot.wi.gov

Hannah Punzel
WisDOT Southwest Region Communications Manager
(608) 246-7907
hannah.punzel@dot.wi.gov

Wisconsin Department of Transportation (WisDOT)
Southwest Region, Madison Office
2101 Wright Street
Madison, WI 53704
Phone: (608) 246-3800
TTY: 711
Email: swr.dtsd@dot.wi.gov