Location
The proposed project on southbound US 53 extends from County Y north to County M in the Douglas County town of Gordon.
Overview
The pavement on US 53 is showing signs of deterioration. To address this, WisDOT is proposing to:
- Repair the concrete pavement.
- Place a 4-inch asphalt overlay over the travels lanes and shoulders.
- Repair or replace culverts.
- Replace guardrail at the St. Croix River Bridge.
- Remove roadside brush and trees.
- Place pavement markings.
Schedule
Construction currently is scheduled for 2027.
Traffic
During construction, US 53 will remain open to traffic, but motorists will encounter single-lane and shoulder closures.
Project Documents
For more information about the project, please review the following for more information:
Contacts - Updated
Adam Hetrick
WisDOT Northwest Region Project Manager
(715) 836-2065
adam.hetrick@dot.wi.gov
Jeff Olson
WisDOT Northwest Region Project Supervisor
(715) 395-3032
jeffrey.olson@dot.wi.gov
Christena T. O'Brien
WisDOT Northwest Region Communications Manager
(715) 833-9814, (715) 828-9471
christena.obrien@dot.wi.gov
Wisconsin Department of Transportation (WisDOT)
Northwest Region, Superior Office
1701 N. 4th St.
Superior, WI 54880
715) 392-7925, (800) 590-1868
nwr.dtsd@dot.wi.gov