WisDOT's Design-Build Program is a collaborative contracting process that brings the engineering and construction industries together at the outset of a highway improvement project. Traditionally in Wisconsin, these processes have always been separated, where a designer plans the project and a construction company will then execute on those plans.
WIS 125 6526-00-71 (March 4, 2022)
- I-41 – Bluemound Dr., OUTAGAMIE, NORTHEAST
- Removal of a multi-cell box culvert and replacement with a slab span structure on College Avenue in Appleton
WIS 130 5770-01-02/72 (February 4, 2022)
- WIS 23 – Lone Rock, Wisconsin River Crossing, RICHLAND, SOUTHWEST
- Construction/replacement of 3 existing bridges across the Wisconsin River with 2 new bridges
Best Value Score Results (June 3, 2022)
US 45 1600-15-00/70 (October 4, 2021)
-
County C – Gollnow Rd, WAUPACA/SHAWANO, NORTH CENTRAL
-
Construction/replacement of 8 miles of pavement on US 45 west of Clintonville