Action plan 1

Process and decision making on disputes, claims, and contract change orders (CCOs)

View Action Plan 1

Accomplishments, action items and milestones
Accomplishments to dateCompletion date
Finalize work planOctober 16, 2014
Short-term action items/milestonesEstimated completion
Complete team assemblyJuly 1, 2014
Finalize project plan developmentFall 2014
Long-term action items/milestonesEstimated completion
Develop trainingFall 2015
Start trainingSpring 2016
Complete trainingSpring 2016

 

Project timeline
Project kickoffOctober 16, 2014
Select expert to review part 1 specificationsDecember 14, 2014
Expert reportJune 2015
Team analysis of expert findingsAugust 2015
Complete analysis of expert findingsFall 2015
Develop trainingFall 2015
Provide trainingFall 2016

 

Project contacts