Action plan 2

Design phase

View Action Plan 2

Accomplishments, action items and milestones
Accomplishments to dateCompletion
Finalize work planJuly 29, 2014
Complete team assemblyJuly 1, 2014
Finalize Project Plan DevelopmentFall 2014
Information transfer processJune 2015
Identify items contributing to blended prices and SPV item issuesMay 2015
FDM and Plan letter changes providing guidance on the posting May 2016
Posting of Question/Answers during bidding periodMay 2016
Long-term action items/milestonesEstimated completion
SPV Reduction is ongoing effort thru the technical committees
Redevelop earthwork training and develop training to address impacts of staging and timing2016

 

Project timeline
Project kickoffMay 15, 2014
Complete analysisMay 2014
Report back to steering teamJune 18, 2014
Develop teamJuly 1, 2014
Plan developmentSeptember 1, 2014
SPV reduction and blended itemsMay 2015
Revise FDMNovember 2015
Earthwork and staging training2016
Complete planSpring 2016

 

Project contacts